20.06.07.00 TEMPORARY USES.


20.06.07.01 Purpose and Scope.
Temporary use provisions allow short-term and minor deviations for uses which are temporary in nature, which will not adversely impact the surrounding properties and land uses, and which can be terminated and removed at will.

20.06.07.02 Permit Required.
(a) Temporary use permits may be granted for the uses listed in Table 6-3 of this section, pursuant to the standards required for that use in Table 6-3 and to Section 20.05.10.00 of this title. Uses not specifically listed in Table 6-3 shall not be permitted.
(b) A specific temporary use permit may be granted only one time per year on any individual zoning lot and is nonrenewable. Fireworks, Halloween pumpkin, and Christmas tree sales are considered separate uses.




(c) A yard, garage, or sidewalk sale is a temporary use which does not require a permit but which is subject to the standards listed for it in Table 6-3.
(d) A drawn-to-scale site plan shall be required which shall demonstrate that the proposed temporary use does not displace required parking for any existing use of the premises, that it does not block existing drives, and that the site is arranged so that no business shall be conducted with vehicles stopped in a public right-of-way.


Table 6-3

STANDARDS FOR TEMPORARY USE

Duration
Where of Permit
Use Permitted (nonrenewable) Conditions

Carnival or circus Any C or 15 days Must be set back at least one hundred feet
I district from any residential district.
Must provide off-street parking.

Christmas tree, Any nonresi- 30 days Lot must front on a collector or arterial
Halloween pumpkin, dential district street.
and 4th of July Must be located at least fifty feet from
fireworks sales residential district.
Must provide off-street parking.
Unsold trees, pumpkins, or fireworks
must be removed within five days after
the holiday.

Contractor’s office Any district Construction All facilities must be removed upon
equipment storage, on or adjacent period completion of construction.
and portable to the con- May not contain sleeping or cooking
lavatories struction site. facilities.

Real estate Any district, on Initial Only the marketing of on-site
sales office the site of the marketing residences shall be permitted.
development for period
which the sales
are taking place.

Religious Any nonresi- 15 days Must provide off-street parking.
tent meeting dential district

Seasonal sale of RE2.5, RE1 4 months Must provide off-street parking.
farm produce Any other Stands must be removed when not in
nonresidential use.
district

Temporary retail Any nonresi- 15 days Off-street parking shall be
or wholesale dential districts required.
activity

Table 6-3 (Continued)

Duration
Where of Permit
Use Permitted (nonrenewable) Conditions

Yard/garage Any district 3 days Maximum of three times per year per site.
sales No permit required.
Any signs must be removed within five
days.

(Ord. 95-21 § 3 (part), 1995).