        "id": "6003",
        "type": "Lane Restriction",
        "department": {},
        "start": "2024-09-23",
        "end": "2024-12-27",
        "title": "Conduit installation along S Walnut St Pike and E Winslow Rd",
        "geography_description": "S Walnut St Pike & E Winslow Rd; S Henderson St & E Winslow Rd",
        "description": "Lineal will be installing conduit for AT&T to connect some of their existing infrastructure at the intersections of E Winslow Rd, S Walnut St Pike, and S Henderson St. The work is estimated to take about 7 days to complete and will include a lane and sidewalk closure at the locations. The work is planned between September 2024 and December 2024.",
        "geography": "GEOMETRYCOLLECTION(LINESTRING(-86.52873739116825 39.13589253529207,-86.52881526461753 39.13599488412237,-86.52887777603895 39.13607704257987),LINESTRING(-86.52880758360358 39.13599840018847,-86.52684219541364 39.13605889434348),LINESTRING(-86.52695179841065 39.13439149649986,-86.52678625012067 39.13439716166707))"
    }
]