closed #203057

Utility Construction Projects

620 W Howe ST

Case Date:
5/30/2025

Oak tree between east sidewalk and street. Black cord hanging from tree, seems electrical. Appears to have cut ends on the ground. I didn’t attempt to see if they’re live.

closed #203056

Utility Construction Projects

620 W Howe ST

Case Date:
5/30/2025

Black cord dangling from tree, looks electrical. Seems to have open cut ends. Unsure if they’re live, I didn’t try to test it.

closed #202606

Utility Construction Projects

3365 E Longview Ave

Case Date:
5/12/2025

This huge break in the road was not properly marked - the cone was well over a foot from the edge - and I hadn't realized how far in it went until it was too late to avoid it. Two of my tires popped, and my car had to be towed. I'd like the city to reimburse me for replacing them, but more importantly, I'd like for them to make sure these holes are properly marked.

closed #202463

Utility Construction Projects

720 W 3rd ST

Case Date:
5/4/2025

Gigabtye Contracted companies placed these while laying lines but have not returned to address their lack of filling in the side. This one just a great example but many if not all are this bad. Easy to fall into or wreck your bike if you don’t see the ruts on all sides. Especially for those of us who walk/ride at night. Where’s the oversight if any? Please fix these.

closed #201500

Utility Construction Projects

2919 N Bankers DR

Case Date:
3/13/2025

Duke Energy has refused to remove a large orange cable that is down on the length of my property (3/4 of an acre). They say someone else needs to take care of it, like maybe a cable company. I am concerned that it is dangerous to kids in my neighborhood and I cannot do yard work around it. Moreover, it is in the utility easement. They said to pick it up and see if it is attached to the utility line and I am unwilling to do that because it seems risky. In any case, no utility should be leaving their waste on my property and they should take responsibility for removing it safely.

closed #201442

Utility Construction Projects

823 N Dunn ST

Case Date:
3/11/2025

Cylindrical hole about 4" radius drilled into street by fiber-optic workers and left unfilled. Dangerous area because there are no sidewalks along at that location, so people are forced to walk on the street. Hole is closest to SW corner of intersection. Ankle-breaker!

closed #201333

Utility Construction Projects

3308 W 3rd St

Case Date:
3/5/2025

whatever person decided to put up a thing of poles at the turn at the light needs to remove them. never had a problem at that turn and almost get into a crash today because of them

closed #201189

Utility Construction Projects

322 E Cottage Grove AVE

Case Date:
2/26/2025

Fiber-optic people bored a hole through the street, then filled it up with gravel instead of asphalt. Now, the gravel has washed away and there is a hole that someone could step in and trip. It is close to the scooter corral on the SW corner of Grant/Cottage Grove.

closed #199476

Utility Construction Projects

455 N College AVE

Case Date:
11/27/2024

The City of Bloomington was doing road construction repairs outside of my building and broke my light pole and never came back to replace or repair!

closed #199405

Utility Construction Projects

1330 N Crescent RD

Case Date:
11/18/2024

about a 10" inch wide hole that's over a foot deep right in the middle of 17th street. I phoned this into 911 10/20/2024, but nothing has been done.