Smith and SR 46 Intersection Improvement
Smith Rd south of SR46
March 12, 2024 to May 2, 2024
Smith rd and SR 46 intersection improvements. This includes new storm pipe, sidewalk,
curbs, and widening of the intersection. This is part of INDOT's project R-41465. Closures include road and sidewalk closures that
will be completed in two phases: north of SR 46 and south of SR 46. The south side will be completed first starting on 3/12/24 and
completing 4/26/34 followed by the north side on 4/29/24 and completing 6/13/24. Road closures will be in place on Smith at the
intersection for both with planned detours to be used. Private access to homes and business to be maintained as soft closures.
11,797 sq ft of pavement excavations, 80 sq ft of non pavement excavations, 87 sq ft of new sidewalk construction, and 2
residential driveway installations are included in the work
Indiana Department of Transportation