Choose types
Allen St. Bridge Bridge between S Morton and S Walnut (150-156 W Allen St) January 7, 2020 to January 7, 2027
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
Planning & Transportation
LINESTRING(-86.53497807455625 39.15560747171148,-86.5349847800788 39.15559811226916)
Poplars Redevelopment 400 E 7th St November 22, 2025 to June 18, 2026
Phase 3 of 4 of the Poplars redevelopment. Closures to be used for construction deliveries and material movement. This phase includes: Single day closure on the east side of Grant for scaffolding installation (11/13/25) and single day (TBD) for removal. Bike lane closure from 11/22/25 to 3/2/26. Closures of the southern sidewalk along E 7th and the east/west alley on the southern side of the property from 11/22/25 to June 18th, 2026.
External Project
LINESTRING(-86.52972234187298 39.16804160976628,-86.52835108743676 39.168028076294235)
Construction for 115 E Kirkwood Lofts 115 E Kirkwood Ave January 28, 2026 to July 28, 2027
Genesis Construction is requesting a pedestrian diversion and intermittent closures, traffic lane shifts and intermittent lane closures, alley closures, and metered parking reservations associated with the project at 115 E Kirkwood Avenue. The request impacts the northern sidewalk on E Kirkwood, the north–south and east–west alleys surrounding 115 E Kirkwood, the east–west travel lanes on E Kirkwood, and the metered parking spaces along the north and south side of E Kirkwood.
External Project
LINESTRING(-86.53245771844563 39.16705931743067,-86.53296069631311 39.16706282003534,-86.53295467260338 39.16667869420775)
ROW2025-10-2011 W 11th from W Fountain Dr. to N. Adams St. January 29, 2026 to March 31, 2026
This phase will include BPW approved lane restrictions and Sidewalk closure that MUST have PROWAG compliant detours.
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.55041877968597 39.17324963255015,-86.54980902406079 39.173241315132316,-86.54717509472646 39.173239928853576,-86.54717330653254 39.173213590377856,-86.54819254603996 39.17321636284109,-86.5482479783323 39.17321913530421,-86.5488577338756 39.173217749088536,-86.54984121056887 39.17321774912028,-86.55013804167255 39.173220521583346,-86.55042056771607 39.17322468029363,-86.55042056771607 39.17324963255015),LINESTRING(-86.54711718704718 39.17323343569453,-86.54417050898479 39.173265213604964,-86.54417050898479 39.17323333018214,-86.54544008802763 39.173230557687845,-86.54620719980586 39.17322224029945,-86.54665244650234 39.17322085405206,-86.54711378637096 39.17321808158903,-86.54711199834077 39.17323471642925))
Bloomington Convention Center Project Lane Restriction 302 S College Ave February 13, 2026 to June 26, 2026
Immediately following phase 2 completion, a lane closure of the eastern southbound lane of College Ave is being requested. This request is to accommodate placement of pedestrian diversion for curb and sidewalk demolition and reconstruction. The traffic control would be in place from February 13th, 2026 through June 26th, 2026
External Project
LINESTRING(-86.53487655624961 39.164488185161105,-86.53489244558577 39.16354881125994)
Poplar Redevelopment 400 E 7th St February 23, 2026 to July 27, 2026
Sidewalk closures, metered parking reservations, and alley closures surrounding the former Poplars Building located at 400 E 7th Street. The request includes the eastern sidewalk and adjacent parking lanes on N Dunn Street, the southern sidewalk on E 7th Street, and the east/west alley between E 6th Street and E 7th Street. The requested closures are to accommodate completion of exterior façade work, including masonry cleaning and sealing, followed by sidewalk reconstruction and perimeter landscaping along the east side of the Poplars Building on Dunn Street. Traffic control on N Dunn Street is proposed to be in place from February 23, 2026, through July 17, 2026. Traffic control on E 7th Street and within the east/west alley between E 6th Street and E 7th Street will remain in place through July 27, 2026, to support final site concrete work and landscaping associated with project completion. F.A. Wilhelm has supplied maintenance of traffic plans for all prop
External Project
LINESTRING(-86.52934633192137 39.168023490778666,-86.52876028302248 39.16801791578442)
Arlington Multifamily Project Lane Closures 1210 W Arlington Rd March 2, 2026 to June 16, 2026
Mayer Najem is requesting lane shifts on W Arlington Rd adjacent to as part of the project located at 1320 W Arlington Rd. This request is for Sanitary sewer and storm upgrades, tapping water for the site, and transportation infrastructure updates totaling 7012 sq ft of non pavement and 7670 sq ft of pavement excavations. The traffic control is planned to be in place starting in early spring, currently estimated to be from March 2nd, 2026 through June 16th, 2025. Mayer Najem has supplied maintenance of traffic plans for all work. As a condition of the issuance of the ROW permit they will also be required to post signage notifying the public about the lane shifts at least 3 weeks prior to closure implementation.
External Project
LINESTRING(-86.547514919906 39.17939904581016,-86.54805384529433 39.179662415790176,-86.54835845521869 39.179889457965004,-86.54879193846948 39.1802981323784,-86.5490848327994 39.18073404869537,-86.54922542261407 39.180897515881156)
High St Multi-Use Path Tree Clearing S High St between Moores Pike and 2nd St March 6, 2026 to April 15, 2026
Tree clearing will be happening along S High St between Moores Pike and 2nd St. Tree clearing is along the eastern side of the roadway. There will be lane closures with flagging for northbound traffic.
Engineering
LINESTRING(-86.5083987666094 39.15055779365551,-86.5083987666094 39.160915565072344)
Arlington Multifamily Utility Work 1210 W Arlington March 9, 2026 to June 16, 2026
Mayer Najem is requesting lane shifts on W Arlington Rd adjacent to as part of the project located at 1320 W Arlington Rd. This request is for Sanitary sewer and storm upgrades, tapping water for the site, and transportation infrastructure updates totaling 7012 sq ft of non pavement and 7670 sq ft of pavement excavations. The traffic control is planned to be in place starting in early spring, currently estimated to be from March 2nd, 2026 through June 16th, 2025.
Engineering
LINESTRING(-86.54747272130943 39.179383055603836,-86.54803768028326 39.179662430757844,-86.54853445455336 39.18009281733603,-86.54874874933653 39.180289133145806)
Centerpoint Relocation Work 1101 W 2nd st March 16, 2026 to April 30, 2026
Miller Pipeline, on behalf of CenterPoint Energy, is requesting sidewalk closures, lane closures, and alley closures associated with utility relocation work along West 2nd Street from South Walker Street to South Maple Street. This work is required to relocate utilities in advance of the 2nd Street Modernization Project.
External Project
LINESTRING(-86.54559158251006 39.16143929955288,-86.54224580331889 39.161434100723596)
Centerpoint Relocation Work 1101 W 2nd st March 16, 2026 to April 30, 2026
Miller Pipeline, on behalf of CenterPoint Energy, is requesting sidewalk closures, lane closures, and alley closures associated with utility relocation work along West 2nd Street from South Walker Street to South Maple Street. This work is required to relocate utilities in advance of the 2nd Street Modernization Project.
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.54560109841951 39.16234877508592,-86.54559226336345 39.1615370044002),LINESTRING(-86.54399753574025 39.16153015397478,-86.54397986562806 39.16233849956615),LINESTRING(-86.54487662382061 39.16198570581051,-86.54340116945455 39.16197543023773),LINESTRING(-86.54328631372546 39.16198228061978,-86.54230120497208 39.161968579855056),LINESTRING(-86.54288431867363 39.1623316492188,-86.54291524136993 39.161540429612614))
ROW2026-02-2258 W Briarcliff Road, from N Kinser Pike to N Valleyview Dr. March 18, 2026 to April 1, 2026
Sections within Fritz Terrace - Single lane closures
Engineering
LINESTRING(-86.54116487854594 39.19414100269063,-86.54306616001388 39.19415902741869,-86.5458570321596 39.19417705193587,-86.54605567351004 39.19421293303142,-86.54626707375624 39.194280727598766,-86.54640800727226 39.194350405337815,-86.546446885497 39.19438618571331,-86.54641043717868 39.19441631658026,-86.54631081173824 39.19434852214377,-86.54620875644696 39.194299559468874,-86.54604838384638 39.194250596716756,-86.54581268475837 39.19422423213055,-86.54529025871426 39.19422423213055,-86.54436933135321 39.194209166722175,-86.54230149677947 39.194190334827795,-86.54203177922396 39.194190334827795,-86.54115458962242 39.19417903572324,-86.54115701958446 39.194141371999564)
ROW2026-02-2310 1100 E Miller March 20, 2026 to March 27, 2026
Lane closure of Olive St.
Engineering
LINESTRING(-86.51874193439428 39.14673097976828,-86.51877590909638 39.14673097976828,-86.51877233270855 39.14662142575432,-86.51874014620037 39.14662142575432,-86.5187437225882 39.14672959303056)
Lineal Utility Relocation for 2nd Street Modernization Project 525 S Walker St March 23, 2026 to March 25, 2026
Alley closure in the north/south alley between Walker and Euclid for forced relocate, riser down from existing aerial to underground directional bore to install 2" duct, and coaxial cable. start date aprox 3/23/2026, work should take 2 days to complete once started.
External Project
LINESTRING(-86.54559071696255 39.16152858956147,-86.54559293491954 39.16180202680104)
ROW2026-03-2330 305 E 18th Street March 23, 2026 to April 6, 2026
3 days of closures between 3/23 and 4/06
Engineering
LINESTRING(-86.53057503568527 39.180268045950044,-86.53056960033356 39.180290516776836,-86.53029783274751 39.18023714858765,-86.53020724360746 39.180234339712456,-86.53019818457734 39.18021748658765,-86.53030689161177 39.18021889102559,-86.53057322392903 39.18026945038696)
ROW2026-03-2330 305 E 18th Street March 23, 2026 to April 6, 2026
Sidewalk closure will not exceed 24 hours
Engineering
LINESTRING(-86.53057076702682 39.18025699113096,-86.53023638507877 39.18014610320793,-86.53018274089848 39.180147489318756)
ROW2026-03-2376 1025 S Walnut March 23, 2026 to March 24, 2026
closure of Davis St East of Walnut
Engineering
LINESTRING(-86.53357483152101 39.154245506184424,-86.53357483152101 39.15420668109272,-86.53338528869607 39.15420668109272,-86.53338886492017 39.154242733005134,-86.53357483152101 39.154242733005134)

Please enable Javascript

To enjoy the best experience, please make sure Javascript is enabled, or switch to a browser that supports Javascript.

This service uses Javascript to display an interactive map of scheduled road closures, which helps visualize where roads are scheduled to close.