Choose types
Allen St. Bridge Bridge between S Morton and S Walnut (150-156 W Allen St) January 7, 2020 to January 7, 2027
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
Planning & Transportation
LINESTRING(-86.53497807455625 39.15560747171148,-86.5349847800788 39.15559811226916)
Poplars Redevelopment 400 E 7th St November 22, 2025 to June 18, 2026
Phase 3 of 4 of the Poplars redevelopment. Closures to be used for construction deliveries and material movement. This phase includes: Single day closure on the east side of Grant for scaffolding installation (11/13/25) and single day (TBD) for removal. Bike lane closure from 11/22/25 to 3/2/26. Closures of the southern sidewalk along E 7th and the east/west alley on the southern side of the property from 11/22/25 to June 18th, 2026.
External Project
LINESTRING(-86.52972234187298 39.16804160976628,-86.52835108743676 39.168028076294235)
Construction for 115 E Kirkwood Lofts 115 E Kirkwood Ave January 28, 2026 to July 28, 2027
Genesis Construction is requesting a pedestrian diversion and intermittent closures, traffic lane shifts and intermittent lane closures, alley closures, and metered parking reservations associated with the project at 115 E Kirkwood Avenue. The request impacts the northern sidewalk on E Kirkwood, the north–south and east–west alleys surrounding 115 E Kirkwood, the east–west travel lanes on E Kirkwood, and the metered parking spaces along the north and south side of E Kirkwood.
External Project
LINESTRING(-86.53245771844563 39.16705931743067,-86.53296069631311 39.16706282003534,-86.53295467260338 39.16667869420775)
Bloomington Convention Center Project Lane Restriction 302 S College Ave February 13, 2026 to June 26, 2026
Immediately following phase 2 completion, a lane closure of the eastern southbound lane of College Ave is being requested. This request is to accommodate placement of pedestrian diversion for curb and sidewalk demolition and reconstruction. The traffic control would be in place from February 13th, 2026 through June 26th, 2026
External Project
LINESTRING(-86.53487655624961 39.164488185161105,-86.53489244558577 39.16354881125994)
Poplar Redevelopment 400 E 7th St February 23, 2026 to July 27, 2026
Sidewalk closures, metered parking reservations, and alley closures surrounding the former Poplars Building located at 400 E 7th Street. The request includes the eastern sidewalk and adjacent parking lanes on N Dunn Street, the southern sidewalk on E 7th Street, and the east/west alley between E 6th Street and E 7th Street. The requested closures are to accommodate completion of exterior façade work, including masonry cleaning and sealing, followed by sidewalk reconstruction and perimeter landscaping along the east side of the Poplars Building on Dunn Street. Traffic control on N Dunn Street is proposed to be in place from February 23, 2026, through July 17, 2026. Traffic control on E 7th Street and within the east/west alley between E 6th Street and E 7th Street will remain in place through July 27, 2026, to support final site concrete work and landscaping associated with project completion. F.A. Wilhelm has supplied maintenance of traffic plans for all prop
External Project
LINESTRING(-86.52934633192137 39.168023490778666,-86.52876028302248 39.16801791578442)
Arlington Multifamily Project Lane Closures 1210 W Arlington Rd March 2, 2026 to June 16, 2026
Mayer Najem is requesting lane shifts on W Arlington Rd adjacent to as part of the project located at 1320 W Arlington Rd. This request is for Sanitary sewer and storm upgrades, tapping water for the site, and transportation infrastructure updates totaling 7012 sq ft of non pavement and 7670 sq ft of pavement excavations. The traffic control is planned to be in place starting in early spring, currently estimated to be from March 2nd, 2026 through June 16th, 2025. Mayer Najem has supplied maintenance of traffic plans for all work. As a condition of the issuance of the ROW permit they will also be required to post signage notifying the public about the lane shifts at least 3 weeks prior to closure implementation.
External Project
LINESTRING(-86.547514919906 39.17939904581016,-86.54805384529433 39.179662415790176,-86.54835845521869 39.179889457965004,-86.54879193846948 39.1802981323784,-86.5490848327994 39.18073404869537,-86.54922542261407 39.180897515881156)
Arlington Multifamily Utility Work 1210 W Arlington March 9, 2026 to June 16, 2026
Mayer Najem is requesting lane shifts on W Arlington Rd adjacent to as part of the project located at 1320 W Arlington Rd. This request is for Sanitary sewer and storm upgrades, tapping water for the site, and transportation infrastructure updates totaling 7012 sq ft of non pavement and 7670 sq ft of pavement excavations. The traffic control is planned to be in place starting in early spring, currently estimated to be from March 2nd, 2026 through June 16th, 2025.
Engineering
LINESTRING(-86.54747272130943 39.179383055603836,-86.54803768028326 39.179662430757844,-86.54853445455336 39.18009281733603,-86.54874874933653 39.180289133145806)
North Jefferson Street North Jefferson Street; 8th to 10th April 27, 2026 to June 30, 2026
Intermittent lane closures will take place for the duration of the project to accommodate storm water improvements and Sidewalk installation.
Engineering
LINESTRING(-86.50719158491388 39.17130354710221,-86.507172758117 39.16955204365513)
ROW2026-02-2297 S Sare Road from E Rogers to Hunters Glen May 1, 2026 to June 30, 2026
Single lane restrictions and sidewalk closures
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.49652821687987 39.13627799335504,-86.49661600011642 39.13685674575609),LINESTRING(-86.49661600011643 39.13687376781348,-86.49663794592556 39.13771635451258,-86.49657210849817 39.138499355335256,-86.49659405430731 39.14008235213879),LINESTRING(-86.49659405430731 39.140065330857084,-86.49661600011645 39.14232912519927))
Patterson, Grimes and Rogers pavement improvement project South Patterson Drive; Rogers to 3rd West Patterson Drive; Rogers to Morton West Grimes Lane; Morton to Walnut South Rogers Street; west Patterson to1st Street South Rogers Street; W 2nd Street to W 3rd Street May 11, 2026 to October 31, 2026
Intermittent lane Closures throughout the project area Road closures on South Rogers Street FINAL DATES TO BE DETERMINED and InRoads to be updated at that time
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.53869085287643 39.16149370607707,-86.53864511829607 39.16450784174452),LINESTRING(-86.53867560801629 39.15934236163693,-86.53870609773645 39.15389278273034),LINESTRING(-86.53869085287634 39.153786387618425,-86.53806581361148 39.153786387618425,-86.53785238556985 39.153739100850316,-86.53695293882285 39.153408092584215,-86.53675475564131 39.153384449077066,-86.53385823221883 39.153348983801436),LINESTRING(-86.53884330147753 39.153786387618425,-86.54129772395659 39.153845496033796,-86.54169409031965 39.15389278273034,-86.54195325294167 39.15405828591804,-86.5422276604238 39.15431836156938,-86.5424868230458 39.15468483017386,-86.5431423520309 39.155122225687194,-86.5432948006321 39.15527590454636,-86.54334053521245 39.155630546786654,-86.54337102493268 39.15589061662678,-86.54660293527776 39.158881350697726,-86.54840182877173 39.16067809422458,-86.5486305016735 39.16089086344556,-86.54914882691754 39.161399142868646,-86.55049037460795 39.16268755565065,-86.55123737275376 39.163455863967755,-86.55195388117932 39.164235983826586),LINESTRING(-86.55193863631918 39.16433054322158,-86.5516947185573 39.164342363136996))
West Kirkwood Ave safety improvements West Kirkwood Avenue; North Pine street to South Rogers Street May 11, 2026 to October 31, 2026
West Kirkwood Avenue will have intermittent lane closures for the duration of the project as well as 10 days of closure FINAL DATES TO BE DETERMINED and InRoads to be updated at that time
Engineering
LINESTRING(-86.54941011754993 39.166728518060665,-86.54941011754993 39.166728518060665,-86.53889067543408 39.16661879811224)
W Club House Dr Closure W Club House Dr, west of N Old SR 37 May 16, 2026 to December 31, 2030
W Club House Dr east of the Sycamore Shelter and to the intersection at N Old SR 37 has been closed. The Sycamore Shelter can still be accessed from the west via Kinser Pike and Club House Dr. A date for re-opening will be contingent upon necessary bridge repairs and is currently not known.
Engineering
LINESTRING(-86.53707976211632 39.19811710429795,-86.53700130750263 39.19812645808193)
ROW2026-04-2436 711 E Cottage Grove Avenue May 21, 2026 to June 25, 2026
3 phases of 3 day closures between the listed dates
Engineering
LINESTRING(-86.52527259943822 39.17263101095142,-86.5252299785262 39.17263149579409,-86.52524094476512 39.173064236598776,-86.52527037828621 39.17306472414509,-86.52527037828621 39.17263221597463)
ROW2026-03-2393 1009 W Allen Street May 21, 2026 to June 11, 2026
10 days of lane closure between listed dates
Engineering
LINESTRING(-86.54422811005446 39.15344293428984,-86.54424889154733 39.15345367773625,-86.54434587184734 39.15339727462441,-86.54432162677234 39.153386531169474,-86.54423503721874 39.153441591358956)
ROW2026-05-2485 1210 E 3rd St May 26, 2026 to June 12, 2026
Alley closure
Engineering
LINESTRING(-86.51871401738929 39.16352579691795,-86.51851681159239 39.1635323034223,-86.51836366240971 39.16352742354408)
ROW2026-03-2398 N Gates Drive May 27, 2026 to June 10, 2026
Lane closure for 2 day between listed dates
Engineering
LINESTRING(-86.57642511173452 39.171117615897145,-86.57640115207337 39.17110936032398,-86.5764197873654 39.17093599306338,-86.57645705794934 39.17093805696186,-86.57643043610365 39.171117615897145)
CBU Sanitary Sewer Maintenance North Washington Street will be closed to through traffic between East 10th Street and East Cottage Grove Avenue May 29, 2026 to June 12, 2026
Beginning early Tuesday, May 26, City of Bloomington Utilities (CBU) will close East 10th Street at North Washington Street to complete sanitary sewer work in the area. The closure is expected to last one working day, though the duration may be shorter depending on field conditions. Following the work on East 10th Street, North Washington Street will be closed to through traffic between East 10th Street and East Cottage Grove Avenue for approximately one week. After that, the closure will shift to North Washington Street between East Cottage Grove Avenue and just south of East 11th Street for an additional week.
Utilities
LINESTRING(-86.53234531533188 39.17170717659417,-86.53233768739898 39.17251536456459)
ROW2026-02-2266 N Dunn Street between 6th Street and Kirkwood Avenue June 1, 2026 to June 10, 2026
Single lane closure
Engineering
LINESTRING(-86.52826708032241 39.16750664697193,-86.52825903369536 39.16719887672377,-86.52822282387366 39.167199916490404,-86.52823087050069 39.16750872649607,-86.5282643981134 39.16750872649607)
2026 Kirkwood Brick Paver Repair Project Kirkwood b/t Dunn and Grant June 1, 2026 to June 14, 2026
2026 Kirkwood Brick Paver Repair Project
Public Works
LINESTRING(-86.52834535896844 39.166555154617555,-86.52974075249998 39.16655902914971)
Axis Fiber Relocation Project S High Street from E 3rd St to Rock Creek Dr June 1, 2026 to June 19, 2026
Three weeks of lane and sidewalk closures along S High Street from E 3rd St to Rock Creek Dr to relocate approximately 4200 ln ft of fiber conduit and hand holes. This project will take us 10-15 days to complete.
External Project
LINESTRING(-86.50852322030218 39.16410991686445,-86.5083404197909 39.146856511235995)
West 2nd Street Modernization and Safety Improvements 2nd Street between Walker Street and Morton Street June 1, 2026 to November 1, 2026
Intermittent lane restrictions and traffic switches will be implemented.
Engineering
LINESTRING(-86.54614342649008 39.161438835305034,-86.53498313659308 39.16139200980018)
ROW2026-04-2420 North Woodlawn Avenue, Between East 13th Street and E 12th Street June 1, 2026 to July 17, 2026
Full road closure for work associated with ROW2026-04-2420
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.52363343342134 39.175180011100736,-86.52357676134712 39.17517835324318,-86.52356235488244 39.17517793180343,-86.52353467405678 39.174556420441746,-86.52351149891358 39.17432510842613,-86.52358971502188 39.17432510842613,-86.52361031242812 39.17454024856099,-86.52361299463715 39.17470763331403,-86.52363445230927 39.17517891077475,-86.52360763021912 39.17517891077475),LINESTRING(-86.52360763021912 39.17517891077475,-86.52357678481546 39.175177871126124))
ROW2026-04-2450 910 South Adams Street June 2, 2026 to June 16, 2026
Lane restriction, 3 days between listed dates
Engineering
LINESTRING(-86.55057558408082 39.15582271305843,-86.55054876199065 39.15582271305843,-86.55054742088616 39.15563760442339,-86.55057692518531 39.15563864436089,-86.55057692518531 39.155821673123626)
Milling and Resurfacing on Pine Meadows Dr Pine Meadows Dr from S Pinehurst Dr to S Twin Oaks Vly June 8, 2026 to June 12, 2026
Lane Restrictions and No Parking on Pine Meadows Dr from S Pinehurst Dr to S Twin Oaks Vly for milling and resurfacing.
Street
LINESTRING(-86.54995432265784 39.136924783918715,-86.54936798479036 39.13693172723114,-86.54906362620265 39.13699421701227,-86.54891592277038 39.1370844799315,-86.54875926761494 39.13721987409343,-86.5486652745217 39.13739692760461,-86.54863841935219 39.13749413326457,-86.54864737107536 39.13804264840192,-86.54863841935219 39.13856338666676,-86.54864289521379 39.13876126619755,-86.54872793658386 39.13904593402066,-86.54893830207831 39.13927158452606,-86.54909048137215 39.13937920220468,-86.54934112962084 39.13949029124876,-86.54965443993173 39.13954930723219,-86.55033924675406 39.13955625028575)
Milling and Resurfacing on Pinehurst Dr Pinehurst Dr from W Tapp Rd to S Rockport Rd June 8, 2026 to June 12, 2026
Lane Restrictions and No Parking on Pinehurst Dr from W Tapp Rd to S Rockport Rd for milling and resurfacing.
Street
LINESTRING(-86.54997062441129 39.13643279955676,-86.54997606634309 39.13738674099403,-86.54997062441129 39.13769909069126,-86.54991076316131 39.13793968343222,-86.54976383100232 39.138154949924626,-86.54952982793428 39.13836599486643,-86.54918698622994 39.13852216771616,-86.54893665736647 39.13858126005542,-86.5486155833894 39.13858970181411,-86.54788092259442 39.13854749301049,-86.54741291645833 39.13850950506557,-86.54708640054943 39.138437750002566,-86.54682518782235 39.1382984605539)
Milling and Resurfacing on S Southern Ridge Ct S Southern Ridge Ct from S Southern Pines Ct to the Dead End June 8, 2026 to June 12, 2026
Lane Restrictions and No Parking on S Southern Ridge Ct from S Southern Pines Ct to the Dead End for milling and resurfacing.
Street
LINESTRING(-86.54754944176256 39.139342895888575,-86.54724849952058 39.13951949236352)
ROW2026-03-2376 1025 S Walnut- Closure on East Davis Street June 8, 2026 to June 9, 2026
Full closure of Davis Street.
Engineering
LINESTRING(-86.53358371756566 39.154245374445054,-86.53358371756566 39.154208975902264,-86.5331921150495 39.15420689598497,-86.5331921150495 39.15424849431929,-86.53358371756566 39.154245374445054)
ROW2026-06-2536 1215 N Woodburn Avenue June 8, 2026 to June 12, 2026
Lane closure of N Woodburn for street cuts.
Engineering
LINESTRING(-86.53596580242116 39.17833628657891,-86.53597087540588 39.1780557681445)
ROW2026-05-2512 430 East 10th Street June 8, 2026 to June 12, 2026
Lane closure for street cuts
Engineering
LINESTRING(-86.52831484096045 39.171602097001426,-86.52830877454355 39.17121997428032)
ROW2026-05-2511 407 North Roosevelt Street June 8, 2026 to June 12, 2026
Lane closure for street cuts
Engineering
LINESTRING(-86.50610895222376 39.169898343900655,-86.50610351415712 39.16959373688758)
ROW2026-06-2535 200 E 17th June 8, 2026 to June 12, 2026
lane closures for street cut
Engineering
LINESTRING(-86.53220805466978 39.17895512994022,-86.53189289511054 39.17895616953302)
ROW2026-06-2535 200 E 17th June 8, 2026 to June 12, 2026
Lane closure for street cut
Engineering
LINESTRING(-86.53222136370036 39.17893696988156,-86.53222136370036 39.1787103382255)
CBU - Concrete work Section of South Euclid Avenue just north of West Second Street June 8, 2026
Beginning Monday, June 8, City of Bloomington Utilities (CBU) will close a portion of South Euclid Avenue just north of West Second Street to through traffic between 8:00 a.m. and 3:00 p.m. so crews can complete concrete work associated with previous water main relocation work in the area. The closure is expected to last one day, weather and field conditions permitting.
Utilities
LINESTRING(-86.543334527948 39.161468003176395,-86.54334410143926 39.161956063192406)
Milling and Resurfacing on S Southern Pines Ct S Southern Pines Ct from W Pinehurst Dr to the Dead End June 8, 2026 to June 12, 2026
Lane Restrictions and No Parking on S Southern Pines Ct from W Pinehurst Dr to the Dead End for milling and resurfacing.
Street
LINESTRING(-86.54744238480099 39.13853134722521,-86.54736604810098 39.13877410137701,-86.54736223126598 39.13896948825712,-86.54740803328599 39.13910566667107,-86.547495820491 39.13924776560475,-86.54757215719101 39.13933953768037,-86.547686662241 39.13941650771605,-86.54785460298103 39.1394934776676)

Please enable Javascript

To enjoy the best experience, please make sure Javascript is enabled, or switch to a browser that supports Javascript.

This service uses Javascript to display an interactive map of scheduled road closures, which helps visualize where roads are scheduled to close.