Lineal Pole and Boring Work
1320 W Arlington Rd
July 14, 2025 to July 16, 2025
A052WWY- Replacement of 3 fiber poles just north of the roundabout of Arlington Rd and N Monroe St and W 17th St. After the poles have been relocated, the fiber on the original poles will be placed on the new poles. The work is expected to take 2 days to complete and will have only 1 lane closure.
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.54760204546919 39.17944752111052,-86.5478302186859 39.17956543664536),LINESTRING(-86.5487274198744 39.180343824854276,-86.54887166736086 39.18053695970096))