Baxter Village Subdivision Utility Work
4415 E Moores Pk
October 14, 2025 to October 20, 2025
10/14/2025 Night:
Cut road remove initial 2- 3 feet and plate 10/16/2025 Day:
Morning: Finish digging to pipe
CBU will tap main early afternoon
Back Fill up to 10.5” of surface
10/17/2025 Day:
Finish any Back filling up to the 10.5” of surface if necessary
Cut back road per plans to (8” x 10.5” on each side of road cut
Pour Flowable fill
10/18/2025 Day:
Roll in asphalt and clean up signs
10/20/2025 Night:
Request this for a closure in case asphalt is not available on Saturday This should only take 2-3 hours to complete. This dig is around 8’ deep, 6’ wide and 1/2 to 3/4 width of the road.