subsurface utility engineering (SUE) fieldwork along N. Dunn Street
1701 N Dunn St
August 17, 2026 08:00 am to 17:00 pm daily until August 21, 2026
Perform subsurface utility engineering (SUE) fieldwork along N. Dunn Street, from E. Vernon Avenue north to approximately 500 feet north of E. Tamarack Trail. Work includes hydro-excavating up to ten 2-foot-by-2-foot test holes in grassy areas to verify the location and depth of gas lines for a proposed trail and drainage project. Each test hole will be backfilled and the previously removed sod restored upon completion. No paved surfaces will be disturbed.
The northbound lane of N. Dunn Street will be temporarily closed near active work areas, with flaggers directing traffic around each work zone. Traffic impacts are expected to last no more than two days.
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.528492564003 39.18663499227401,-86.52859038389741 39.19848709348537),LINESTRING(-86.5283295308455 39.18587679410908,-86.52839474410847 39.179229573391126))