Allen St. Bridge
Bridge between S Morton and S Walnut (150-156 W Allen St)
January 7, 2020 to January 7, 2027
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
Planning & Transportation
LINESTRING(-86.53497807455625 39.15560747171148,-86.5349847800788 39.15559811226916)
N Headley Rd
N Headley Rd/N Hinkle Rd from E Maplecrest Dr to E Gramercy Park Dr
November 15, 2021 to July 6, 2022
The southbound lane of N Hinkle Rd/ N Headley Rd will be closed for the construction of improvements to the Lake Griffy causeway.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.51174219411425 39.19061370527572,-86.51183395760373 39.192427270196475,-86.51229277505114 39.19306734075863,-86.51229277505114 39.19370740549047,-86.5121551298169 39.19427634702424,-86.51311864645642 39.19672985461864,-86.51334805518013 39.19886326984221,-86.5142656900749 39.20039217756835),LINESTRING(-86.51431157181965 39.2006055108848,-86.51343981866961 39.20035662195261,-86.51022809653789 39.20177883254502),LINESTRING(-86.50999868781419 39.20213438069416,-86.50981516083526 39.203521001280876,-86.50825518151413 39.20440984623457))
Tapp & Deborah Signal Installation
The intersection of West Tapp Road and South Deborah Drive
February 28, 2022 to July 1, 2022
Lane restrictions will be in place for the construction of a new traffic signal at the intersection of West Tapp Road and South Deborah Drive.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.56816662571836 39.13664684166346,-86.56755599776871 39.13662624908605),LINESTRING(-86.56786573658376 39.13679098953668,-86.56787458626418 39.13647523666771))
Kirkwood Closure for Street Dining
E. Kirkwood Ave. Indiana to Dunn, Dunn to Grant, and Half block from Walnut to Alley.
March 21, 2022 to October 31, 2022
Kirkwood has been closed through October 31st to all East West traffic in the areas outlined. North/South roads are still passable and open during the duration of the temporary closure. Any questions please contact Department of Public Works @ 812-349-3410.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53344102010841 39.1665727662801,-86.53288173397176 39.1665727662801),LINESTRING(-86.5298001770228 39.1665727662801,-86.52834164650959 39.16655576149904),LINESTRING(-86.52815521779738 39.16655576149904,-86.52700374633957 39.16653875671389))
Walnut Street Traffic Signals.
The intersection of 11th Street and Walnut Street and the intersection of 14th Street and Walnut Street.
April 1, 2022 to July 29, 2022
Lane restrictions will be in place for the construction of new traffic signals at 11th and Walnut and 14th and Walnut.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.53363370488768 39.175966543620945,-86.5333855020016 39.175966543620945),LINESTRING(-86.5337282583681 39.17330025069447,-86.53346823629695 39.17330025069447),LINESTRING(-86.53353915140727 39.17306202028945,-86.53349187466705 39.176113140986985))
CBU Stormwater Project
Intersection of S Montclair Ave & E Queens Way
April 27, 2022 to June 24, 2022
CBU staff will be replacing stormwater infrastructure at the intersection of S Montclair Ave and E Queen's Way. Work is scheduled to begin 4/27/22 and end 5/20/22. Traffic will intermittently be down to 1 lane with street signs and/or flaggers.
Utilities
LINESTRING(-86.50541278252597 39.14632777200151,-86.50428142900539 39.14625045264708,-86.50322376504977 39.14620002696046,-86.50428142900539 39.14624709098706,-86.50435142121981 39.147145842912664,-86.50427653816791 39.14493069603819)
E 7th St
E 7th St from Union to Overhill
May 2, 2022 to June 30, 2022
Neighborhood Greenways Project:
There will be EB/WB lane closures on E 7th St from Overhill DR to Union St, and NB/SB lane restrictions on Union St at the intersection of 7th St. This is a City project installing an East-West bicycle/pedestrian corridor connection.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.50942601004849 39.168207688306296,-86.50345219426148 39.168207688306296,-86.50341786120029 39.16772856903415),LINESTRING(-86.50341786120029 39.16772856903415,-86.50333203051183 39.16772856903415,-86.50150383658533 39.167695296744824,-86.5009974360472 39.168240960353245))
Hidden River Project
4th & Grant
May 3, 2022 to July 31, 2022
4th street from Grant to the Taste of India parking lot remains closed.
Grant closed from 4th street to the alley south of Soma and Trinity Church.
Access to Soma and the Venue will still be open via Grant and the alley.
This is for for sanitary and storm culvert construction (Hidden River Project)
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.53104123673921 39.16556598269074,-86.5298335207164 39.16556947672066,-86.53049145560712 39.16556947672066),LINESTRING(-86.52981098875553 39.16606561204634,-86.52982000158937 39.1655764645881))
17th Street Multi-Use Path East Project
East 17th Street from North Walnut Street to North Grant Street
May 9, 2022 to August 6, 2022
Temporary lane restrictions possible with flaggers in place.
Planning & Transportation
LINESTRING(-86.53342624591883 39.1790076068763,-86.53224114554412 39.17898655278853,-86.52965213245436 39.17899936305173,-86.52865508698788 39.178997228008,-86.52836313444797 39.17902925365681)
Curry Pike
Curry Pike and Woodyard Road Intersection
May 9, 2022 to October 7, 2022
Curry Pike, Smith Pike and Woodyard Road Intersection. Lane restrictions on Curry Pike. Woodyard Road, west of Curry Pike is closed.
Monroe County Highway Department
POINT(-86.5825252755342 39.190266765555606)
S Grant St
E 3rd St to E 4th St
May 11, 2022 to April 23, 2023
S Grant St will be closed to northbound traffic for the duration of the development project. Southbound remains open.
Planning & Transportation
LINESTRING(-86.52982079371706 39.164661792515574,-86.52982079371706 39.16552172880188)
City Hall Lighting Project
N Morton Street from W 7th Street to W 10th Street
May 23, 2022 to June 24, 2022
5 Star Electric will be replacing the street lights along the west side of N Morton St for the City of Bloomington from 7:00 am to 7:00 pm Monday through Thursday.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53613735684509 39.168594944749174,-86.53612085430098 39.17165270895782),LINESTRING(-86.53612085430098 39.17165270895782,-86.53615385938917 39.17163991524231))
Crosswalks Project
11th and Blair.
May 31, 2022 to August 31, 2022
Road and sidewalk construction workzone. Lane restrictions possible with flaggers.
Planning & Transportation
LINESTRING(-86.54424947249863 39.17326849138044,-86.5437457933473 39.173273990983915)
Crosswalks Project
Intersection of 3rd and Patterson.
May 31, 2022 to August 31, 2022
Road and sidewalk construction work zone.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.55129479728153 39.16348685392569,-86.55122371874262 39.16340990709253),LINESTRING(-86.55120226107049 39.163483734461124,-86.55132430158068 39.163414066382984))
Crosswalks Project
3rd and Grant intersection.
May 31, 2022 to August 31, 2022
Road and sidewalk construction work zone. Lane restrictions.
Planning & Transportation
LINESTRING(-86.53004510060686 39.164584942304856,-86.52957169071574 39.164579743278324)
W 17th St
W 17th St from N College Ave to N Walnut St
June 13, 2022 to June 20, 2022 daily until June 24, 2022
W 17th St will be fully closed for utility work in the intersection of 17th and Walnut. There will also be lane restrictions on N Walnut St.
Planning & Transportation
LINESTRING(-86.53456893056422 39.178995247265476,-86.53353967051717 39.178976400227555)
N Walnut St
E 15th St to E 17th St
June 13, 2022 to August 12, 2022
There will be lane restrictions on N Walnut St for utility work.
Planning & Transportation
LINESTRING(-86.53348519149894 39.17892144641405,-86.53349631357625 39.1768867245616)
E 17th St
N Lincoln St to N Grant St
June 15, 2022 to June 17, 2022 daily until June 24, 2022
The street will be closed for utility work.
Planning & Transportation
LINESTRING(-86.53086756264887 39.178965541170356,-86.52970469562128 39.178992857139434)
N Walnut St
E 19th St to the Bypass
June 20, 2022 to July 1, 2022
Lane restrictions will be in place for utility work.
Planning & Transportation
LINESTRING(-86.53367979728205 39.18149840055963,-86.53422987960802 39.18435677161446)
E 19th St
N Walnut St to N Lincoln St
June 20, 2022 to August 12, 2022
Lane restrictions will be in place for sidewalk construction.
Planning & Transportation
LINESTRING(-86.53362854403883 39.18145887212131,-86.53098465366067 39.18111318783954)
South High/ East Hunter
South High/ East 2nd St
Northwest and Southwest Corners of South High/ East Hunter & South High/ East 2nd Street
June 21, 2022 to June 24, 2022
ADA Ramp replacement, 6:00 am to 4:00 pm, Monday through Thursday , weather permitting.
Street
GEOMETRYCOLLECTION(LINESTRING(-86.50874574055965 39.16221183714609,-86.50851172578099 39.162207976593436,-86.50851670481885 39.16232765362767,-86.50851670481885 39.1620805782365),LINESTRING(-86.50851670481885 39.1620805782365,-86.50851172578099 39.1620805782365),LINESTRING(-86.50876565671102 39.16101505567147,-86.50848683059179 39.161022776907515,-86.50848683059179 39.161188783277765),LINESTRING(-86.50848683059179 39.16118106205994,-86.50848185155395 39.161188783277765),LINESTRING(-86.50848185155395 39.161188783277765,-86.50847189347824 39.161188783277765),LINESTRING(-86.50848185155395 39.16118492266898,-86.50849180962962 39.160860630772305))
W 17th St
N College Ave to N Walnut St
June 22, 2022 to June 30, 2022
W 17th St will be fully closed for utility work.
Planning & Transportation
LINESTRING(-86.53457131354998 39.17898126450447,-86.5335689190477 39.17896687501306)
N Walnut St
E 14th St to E 17th St
June 22, 2022 to August 12, 2022
Lane restrictions will be in place for utility work.
Planning & Transportation
LINESTRING(-86.53351013374385 39.17601383440231,-86.5334897106066 39.178958561944455)
North Union Street
North Union north and south of East 10th Ave intersection.
June 23, 2022
Milling and filling approaches.
Street
LINESTRING(-86.50945637240088 39.17163570751006,-86.50945503129638 39.171484950698726)
North Union St
North Union Street from East 10th Street to Law Lane
June 27, 2022 to June 28, 2022
Milling and paving approach, weather permitting
Street
LINESTRING(-86.50945648285898 39.171587011882735,-86.50944913524211 39.17195584617383,-86.50952995902784 39.17211534148436,-86.50966221613179 39.172318982292495)
CBU Road Closure - W Chambers Dr
W Chambers Dr & S Roger St
June 27, 2022 11:00 am to 15:00 pm
Please be advised that CBU crews have closed W Chambers Dr west of S Rogers due to water main break. Normal traffic flow is expected to resume at 3pm. Road signs are in place.
Utilities
LINESTRING(-86.5389446528614 39.14635825306536,-86.54031872634152 39.146372274685945)
East 2nd Street
East 2nd Street from South High to S Swain Ave
June 27, 2022 to July 11, 2022
ADA Ramp/ Sidewalk replacement - Monday through Thursday from 6:00 am till 4:00 pm, weather permitting
Street
LINESTRING(-86.51526459466386 39.16104809810619,-86.50849466003378 39.16100306792205)
North Fess
North Fess between E 10th St and E 9th St
June 28, 2022
Closed from 7:00 am until appropriately 10:00 am for tree removal.
Street
LINESTRING(-86.52583188639647 39.171643738418766,-86.52581516012948 39.170463717069964)
W 6th St
W 6th St from N Fairview St to N Jackson St
June 28, 2022 to June 30, 2022
Tree/Stump removal
Street
LINESTRING(-86.54091026189657 39.16759896743787,-86.53982965909903 39.16759749244969)
East 7th Street
East 7th Street From North Union to North Ovehill Drive/East 8th Street
June 28, 2022 to July 14, 2022
Milling/ Paving Monday through Thursday (Excluding July 4th) , 6:00 am till 4:00 pm, weather permitting
Street
GEOMETRYCOLLECTION(LINESTRING(-86.50944910554671 39.16820879145283,-86.50344493763969 39.16821835980099),LINESTRING(-86.5034387668608 39.16772558817706,-86.50149497149522 39.16769209871808,-86.50045210985463 39.167605982893235,-86.50151348383203 39.16769209871808,-86.50122345722193 39.167960013943286,-86.50099513840121 39.168266201522385),LINESTRING(-86.50099513840121 39.168266201522385,-86.50100130918015 39.168256633180675),LINESTRING(-86.50099513840121 39.168266201522385,-86.50100130918015 39.168247064837715))
West 13th Street
West 13th Street from North Maple Street to North Jackson St
June 29, 2022 to July 15, 2022
ADA Ramp/Sidewalk replacement- weather permitting
Street
LINESTRING(-86.54210256874082 39.17506488924846,-86.53971902466141 39.17506137971412)
Hidden River Project
Lincoln btw 3rd & 4th
July 1, 2022 to July 14, 2022
Lincoln remains closed between 3rd and 4th for for sanitary and storm culvert construction (Hidden River Project)
External Project
LINESTRING(-86.53106564427502 39.16557033684904,-86.53108731834105 39.1646685009633)
Hidden River Project
Alley East of Grant
July 1, 2022 to July 31, 2022
Alley east of Grant between Kirkwood and 4th remains closed for for sanitary and storm culvert construction (Hidden River Project)
External Project
LINESTRING(-86.52977517097028 39.16607306906232,-86.52917641773409 39.16606152122435)
Indiana University Jacobs School of Music Summer Concert
Eagleson Avenue from Jones St to south of Parking Garage
July 6, 2022 18:50 pm to 20:10 pm
Indiana University Jacobs School of Music Summer Concert
Public Works
LINESTRING(-86.51639915845762 39.16543079290366,-86.51641080285182 39.166450971864236,-86.51635258088075 39.16672181335039,-86.51615462617909 39.166956541794804)
Hidden River Project
4th & Lincoln
July 11, 2022 to July 14, 2022
Intersection of 4th & Lincoln closed for sanitary and storm culvert construction (Hidden River Project)
External Project
LINESTRING(-86.53120831556659 39.165664032954965,-86.5309562835534 39.16550770786091,-86.53107149833994 39.16559145347685,-86.53100669005272 39.16568078201141,-86.5311723113386 39.16551329089259)
CBU Water Main Replacement
20th from Dunn to Lincoln and Lincoln from 20th to 19th
July 11, 2022 to August 26, 2022
CBU crews will have 20th from Dunn to Lincoln and Lincoln from 20th to 19th closed for a water main replacement project from July 11 to Aug 26.
Utilities
LINESTRING(-86.52833827370313 39.18175593204384,-86.53090129650754 39.18182564134628,-86.53092827569496 39.181135516206695)
Dunn St Sidewalk Project
N Dunn St from 15th to 16th St
July 13, 2022 to September 10, 2022
The southbound lane of N Dunn St from 15th to 17th will be closed for the construction of a sidewalk and tree plot from 15th to 16th St. A detour will be in place to direct vehicular traffic. The northbound lane will remain open to northbound vehicles.
Planning & Transportation
LINESTRING(-86.52834309359234 39.17885144367111,-86.52834309359234 39.17686870194311)
East 7th St
East 7th Street From North Hillsdale to North Ovehill Drive/East 8th Street
July 14, 2022 to July 20, 2022
Milling and Paving, weather permitting, 6:00 am till 4:00 pm
Street
GEOMETRYCOLLECTION(LINESTRING(-86.50341651492144 39.16773332753263,-86.50146934729021 39.16769901753227,-86.50099361883483 39.16826084168105),LINESTRING(-86.50144168865907 39.167677573773545,-86.50046257311723 39.167608953701716),LINESTRING(-86.50046257311723 39.167608953701716,-86.50047363656968 39.167613242458174))
Temporary Lane Closure
N. Walnut Street north of 7th Street
July 14, 2022 08:30 am to 14:00 pm
Contractor will be installing a new window in the Walnut Street Parking Garage. The Eastern lane of N. Walnut will be temporarily closed to facilitate this work.
Public Works
LINESTRING(-86.53355133960436 39.168603132421,-86.53354086460737 39.169139127456816)
North Jefferson St
North Jefferson Street from East 10th to East 8th Street.
July 18, 2022 to July 22, 2022
ADA ramp replacement , weather permitting, 6:00 am to 4:00 pm- Monday through Thursday
Street
LINESTRING(-86.50719462150126 39.1713557214627,-86.50717639222773 39.16950434833299)
AMI ROOFING
200 N WALNUT ST
July 19, 2022 06:00 am to 20:00 pm August 1, 2022
METERS 206A&B, 208A&B
Public Works
GEOMETRYCOLLECTION(POINT(-86.5336731798706 39.1679371956545),LINESTRING(-86.5336731798706 39.167953831743915,-86.5336731798706 39.16822000863951),LINESTRING(-86.53371609521486 39.16822000863951,-86.53365172219848 39.16820337261308))
CBU Road Closure - S High
1212 S High St
July 19, 2022 21:00 pm to 06:00 am July 20, 2022
Please be advised that CBU crews have closed S High between E Southdowns Dr and S Covenanter Dr due to manhole replacement. Normal traffic flow is expected to resume at 6am. Road signs are in place.
Utilities
LINESTRING(-86.5084571838002 39.15542936297379,-86.50842562563378 39.15426697124775)
Greenways Project
Graham, Ralston, and Bryan St intermittent lane closures
July 19, 2022 to July 31, 2022
Intermittent lane closures along Graham, Ralston and Bryan for traffic calming device installation
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.54504986539094 39.13999594122507,-86.53642273664414 39.13975228174726,-86.53615691474998 39.1370719718343),LINESTRING(-86.53850098054393 39.13838402440092,-86.54633064360826 39.138552715099934))
N Jefferson Street
North Jefferson Street from East 3rd St to East 10th Street
July 20, 2022 to July 28, 2022
Milling/Paving, weather permitting, 6:00 am till 4:00 pm, Monday through Thursday.
Street
LINESTRING(-86.50711585644267 39.164274419902966,-86.50714477722352 39.16681382328437,-86.50720261878512 39.17134864452356)
Periodic One Lane Road on W 17th St
W 17th between N Monroe and N Kinser Pike
July 20, 2022 07:00 am to 17:00 pm daily until August 3, 2022
CenterPoint Energy/Miller Pipeline will have periodic lane restrictions on W 17th to accommodate utility relocations. Flaggers will be on site. It is not anticipated that all days will require lane restrictions and INRoads will continue to be updated if the schedule does change. Crews on site will help accommodate the safe passage of pedestrians
Planning & Transportation
LINESTRING(-86.54459344113705 39.179022280488255,-86.53927573922073 39.17899852167122)
Banneker Center Block Party
N Elm between W 7th and W 8th
July 22, 2022 15:00 pm to 20:00 pm
Banneker Center Block Party
Parks & Recreation
LINESTRING(-86.54527598089172 39.16869589482155,-86.54526261352605 39.16954571635594)