Allen St. Bridge
Bridge between S Morton and S Walnut (150-156 W Allen St)
January 7, 2020 to January 7, 2027
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
Planning & Transportation
LINESTRING(-86.53497807455625 39.15560747171148,-86.5349847800788 39.15559811226916)
AEG Lane and Sidewalk Closure for Fiber Installation
S Maxwell St, E Hillside Dr, S Olive St, S Highland Ave, S Nancy St, E Thornton Dr
February 3, 2023 to August 3, 2024
City wide Fiber, BLC02a-F14_ S Maxwell St, E Hillside Dr, S Olive St, S Highland Ave, S Nancy St, E Thornton Dr; The Board of Public Works extended this permit on May 21st, 2024. Substantial completion is expected on August 3rd, 2024.
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.51744301254095 39.146825670225866,-86.51623242922997 39.146825670225866,-86.51506586713032 39.146825670225866,-86.5150988830388 39.14825952729285),LINESTRING(-86.5208436511146 39.15055534474067,-86.52085465641743 39.146893949796095,-86.51881867539443 39.14685127507241,-86.51882968069724 39.14930076233048),LINESTRING(-86.516936768611 39.15049560322828,-86.51694777391381 39.149778701123864,-86.51744301254104 39.14916420779335,-86.51750904435801 39.14830220116261,-86.5180372988937 39.14830220116261,-86.51747642577749 39.14829062414094,-86.51514290425018 39.14824245773758,-86.51513189894735 39.15049560322828),LINESTRING(-86.51071877251371 39.14848996588256,-86.51320597095261 39.14848143113343,-86.51387729442506 39.14829366639074,-86.51436152774946 39.14824245773758,-86.51514290425018 39.148259527292794),LINESTRING(-86.51999624279688 39.15056387923829,-86.5169361821052 39.1505390187622,-86.51513151050528 39.15052435728575,-86.51103741071513 39.15049109607182,-86.50954085377863 39.15047893776625,-86.50844067482848 39.15046999970741),LINESTRING(-86.5217791018549 39.15055534474067,-86.5208436511146 39.15055534474067,-86.51994121628277 39.15055534474067),LINESTRING(-86.51111452130881 39.15297910047539,-86.51213801447173 39.15297056627065,-86.5121710303802 39.15378984520481,-86.51299642809224 39.15355942396869),LINESTRING(-86.51214901977455 39.15297910047539,-86.51219304098586 39.15242437501533,-86.51239113643673 39.152321963682994,-86.51295240688093 39.15242437501533),LINESTRING(-86.51238013113392 39.152321963682994,-86.5125342053735 39.15208300332796,-86.51256722128198 39.15185257650285,-86.51251478425085 39.15133197978665,-86.512569810765 39.150589482724854),LINESTRING(-86.50841822211618 39.15265479996816,-86.51104848949186 39.152620662985726,-86.51106416260086 39.15298041977641,-86.51110351600597 39.15388372030691),LINESTRING(-86.51108409488333 39.15265479996816,-86.51109510018617 39.15056387923818),LINESTRING(-86.51103792629566 39.150452930688374,-86.51071877251367 39.15017129127605,-86.51069676190804 39.14994939276349,-86.51066374599954 39.14901911830728),LINESTRING(-86.50954120511118 39.150452930688374,-86.50951919450553 39.14890816732208),LINESTRING(-86.50844023272184 39.15261212873753,-86.50844023272184 39.150469999707326),LINESTRING(-86.51557211106032 39.14099605768655,-86.51574819590556 39.14143991046657,-86.51644152998365 39.142882412674965,-86.51671666255434 39.143070191853155,-86.51736597542113 39.14320675821361,-86.51742100193526 39.14343721334606,-86.5174320072381 39.144452914013414),LINESTRING(-86.52050248672688 39.14443584353501,-86.5201062958251 39.144307814815306,-86.51969909962051 39.14394079786163,-86.51937994583851 39.14422246220616,-86.51904978675371 39.14439316732097),LINESTRING(-86.51747602844945 39.148302201162636,-86.51745910346794 39.146825559301334,-86.51743200723814 39.14446144925097,-86.51875264357737 39.14444437877469,-86.51902777614806 39.14439316732097,-86.51947899356396 39.1450077023066,-86.52002925870532 39.1451954758154,-86.52059052914949 39.14521254610955),LINESTRING(-86.51878565948587 39.14685981001924,-86.51875264357737 39.14533203805263),LINESTRING(-86.51505486182748 39.14680006536989,-86.51504385652467 39.14400054493805,-86.51601232317343 39.14402615081241),LINESTRING(-86.51630946634978 39.14559662663339,-86.51623242922997 39.14680860032291))
AEG Lane and Sidewalk Closure for Fiber Installation
N Hay St, W 8th St, N Adams St, W 11th St, N Blair Ave, N Orris Dr, Moravec Way, W Cottage Grove Ave
March 31, 2023 to July 27, 2024
City wide Fiber, BLN01b-F12_N Hay St, W 8th St, N Adams St, W 11th St, N Blair Ave, N Orris Dr, Moravec Way, W Cottage Grove Ave; The Board of Public Works extended this permit on May 21st, 2024. Substantial completion is expected on July 27th, 2024.
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.54969893865396 39.169769992437836,-86.55009957705968 39.169992247993434,-86.55216931624417 39.17114043185137),LINESTRING(-86.5501161579803 39.16997428323674,-86.55048945948282 39.16967635895671,-86.55035770601134 39.16960826180119,-86.54985265103736 39.16960826180119),LINESTRING(-86.54965479088648 39.16979052110614,-86.54962586820342 39.17039594244102,-86.54979940430172 39.171270430723524,-86.54981868609042 39.173236121098995),LINESTRING(-86.54978976340736 39.17126295651079,-86.54823757941709 39.17128537914664,-86.54723492640476 39.1713003275666,-86.54704210851776 39.171419914811736,-86.54709995388386 39.17226449394059),LINESTRING(-86.54924987332379 39.17226449394059,-86.54823757941709 39.17226449394059,-86.54822793852276 39.173221173090525),LINESTRING(-86.54713851746126 39.17326601710633,-86.5471095947782 39.17226449394059,-86.54824722031144 39.17226449394059),LINESTRING(-86.55251948628741 39.17325225724946,-86.54981871874423 39.173255056369186,-86.54822799979746 39.17325670501626,-86.54713850334984 39.17325783418815,-86.54484453045023 39.17326021169907,-86.54378084534648 39.1732613141196,-86.54214339553842 39.17326301119917,-86.54107211984486 39.17326412148668,-86.54104151191318 39.17507339422764),LINESTRING(-86.5421357454702 39.17508525815754,-86.5421433974531 39.17326412148668),LINESTRING(-86.54714779428033 39.17643773304579,-86.54715544626325 39.17503780242589,-86.5460918206379 39.17502593848798,-86.54575513338959 39.17494882284271,-86.54508941087589 39.174646291417645,-86.54486750337132 39.174385282867746,-86.54484454742257 39.17327005360451),LINESTRING(-86.54378092179722 39.17330564630103,-86.54384213766056 39.174942890866504,-86.54407169714804 39.17515644169498,-86.54435482051593 39.17529880855366),LINESTRING(-86.53964605760852 39.17904145263867,-86.54205727256635 39.17902969719697,-86.54209439158838 39.17661985298605,-86.54211793206215 39.17509151360184,-86.54104122601179 39.1750797574997,-86.54105639088576 39.17661979014355,-86.54020715794461 39.17660803429692),LINESTRING(-86.5411018855076 39.17663154598819,-86.54208760231425 39.17661979014355),LINESTRING(-86.5556717626943 39.16964231038716,-86.55483732404161 39.16963379824222,-86.55482634458568 39.170629712210314),LINESTRING(-86.55349783041491 39.16959974965209,-86.55350880987089 39.168646382436236,-86.55485928295353 39.168646382436236),LINESTRING(-86.55485928295353 39.16965082253108,-86.55351978932683 39.16960826180119,-86.55351978932683 39.170536079873784),LINESTRING(-86.55350880987089 39.16863787017073,-86.55237792590734 39.16862935790422,-86.55220225461204 39.16870596826584,-86.55221323406799 39.169591237502004,-86.55218029570014 39.17045947150572),LINESTRING(-86.553475871503 39.16961677394923,-86.55086276098535 39.16959974965209,-86.55047848002687 39.169667846815855))
Kirkwood Outdoor Dining
100, 400, & 500 blocks of E. Kirkwood Ave.
Kirkwood Ave. between Indiana Ave and Grant St. Half block between Washington St. and Walnut St.
April 3, 2023 to September 30, 2023
Return of outdoor dining on Kirkwood Avenue. North/South streets will remain open during duration of closure.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53351607551599 39.16658383116999,-86.53289704192028 39.16656669028305),LINESTRING(-86.52966922388542 39.1665495493919,-86.52829850663773 39.1665495493919),LINESTRING(-86.52803320652528 39.16651526759716,-86.52701622276088 39.16649812669351))
Old SR 37 North
Between Bethel Lane and Old Meyers Road
April 3, 2023 to December 15, 2023
The roadway will be closed for the Bicentennial Pathway project. School bus routes and and EMS access will be coordinated and maintained. Detour route is Sample Road/I69/Business 37 North or Old Meyers Road/Boltinghouse Road/Bethel Lane
Monroe County Highway Department
LINESTRING(-86.52156949786387 39.2153847781305,-86.51995243479962 39.21789045268619,-86.517577373424 39.22055263391931,-86.51621297646354 39.225289500880564,-86.51414111441247 39.225994131462556,-86.51161445337458 39.22795140151797,-86.51035112285564 39.22873429425661,-86.50843086046685 39.22951717826177,-86.50630846519499 39.23174834976189)
Intersection of Law Ln and Fee Ln.
Intersection of Fee Ln and Law Ln. Full road closure and sidewalk closure
May 15, 2023 to June 30, 2023 daily until June 30, 2023
IU will be updating steam facilities at the intersection of Law Ln and Fee Ln. The road here will be closed as well as the sidewalks between Law Ln and the RR overpass to the south. Vehicular traffic is to use E 17th St to the north and E 10th St to the south for detouring around the construction.
Planning & Transportation
LINESTRING(-86.51888413009092 39.17403594369716,-86.51888413009092 39.17377635682533)
Winslow Resurfacing Project
Winslow Road from Walnut Street to Allendale Drive.
June 5, 2023 to September 5, 2023
Milling and resurfacing of Winslow Road from Walnut Street to Allendale Drive. Lane restrictions will be in place.
Planning & Transportation
LINESTRING(-86.53104885452514 39.13595805746746,-86.51589852616146 39.13595805746746)
West Country Club Drive Resurfacing Project
West Country Club Drive from Walnut Street to approximately 400 feet west of Walnut Street.
June 5, 2023 to September 5, 2023
Milling and resurfacing of Country Club Drive from Walnut Street to approximately 400 feet west of Walnut Street. Lane restrictions will be in place.
Planning & Transportation
LINESTRING(-86.53274461330035 39.13594162515892,-86.53117634333057 39.135947960729425)
East 3rd Street Resurfacing Project
East 3rd Street from Eagleson Avenue to Overhill Drive.
June 5, 2023 to September 5, 2023
Milling and resurfacing of East 3rd Street from Eagleson Avenue to Overhill Drive. Lane restrictions will be in place.
Planning & Transportation
LINESTRING(-86.51636113081834 39.16424635299623,-86.50161771039184 39.1642192328369)
W 17th Street Multi-use Path
West 17th Street from North Monroe Street to North Walnut Street.
July 14, 2023 to November 3, 2023
Construction Zone. Possible intermittent lane restrictions possible.
Planning & Transportation
LINESTRING(-86.54686175154718 39.17902553972738,-86.5465336338157 39.179086279969795,-86.54604880336066 39.179036928517064,-86.54212118530445 39.1790179475648)
Hopewell Project
South Morton Street from West 1st Street to West 2nd Street.
August 7, 2023 to November 30, 2024
South Morton Street from West 1st Street to West 2nd Street will be closed to through traffic. Detour in place.
Engineering
LINESTRING(-86.53630036983884 39.159437140754676,-86.53628425635348 39.16133312709155)
S Franklin Road
S Franklin Rd from W 3rd Street to End of City Maintenance
August 7, 2023 to August 18, 2023
Milling and resurfacing of Franklin Drive. Lane restrictions will be in place.
Street
LINESTRING(-86.57052330079952 39.16903175509961,-86.5709659777864 39.1684005070843,-86.57101340746355 39.168130846010826,-86.57106874208694 39.167370886513794,-86.57109245692551 39.16610835500347,-86.5711082668179 39.16502354040995,-86.57103712230214 39.16494386410233,-86.5702782474675 39.164913219344584,-86.57020710295174 39.16485805874703,-86.57020710295174 39.16471096360863)
Holiday Drive
Holiday Drive from S Franklin Road to S Fairfield Drive
August 7, 2023 to August 18, 2023
Milling and resurfacing of Holiday Drive. Lane restrictions will be in place.
Street
LINESTRING(-86.57104822323586 39.16772253668182,-86.57004260307343 39.16771928810786)
South Fairfield Drive
South Fairfield Drive from Holiday Dr to S Franklin Road
August 7, 2023 to August 18, 2023
Milling and resurfacing of Franklin Drive. Lane restrictions will be in place.
Street
LINESTRING(-86.57004107626427 39.16768320611931,-86.57007766344928 39.16509374097171,-86.57020310522641 39.16490732822166)
Lane Restrictions on N Walnut St
N Walnut St from approximately E 15th St to E 17th St
August 21, 2023 to August 25, 2023
Landmark Construction and RH Marlin will have the eastern-most lane on N Walnut Street restricted to complete utility work. Signage will be in place to direct motorists to use the western-most lane
Engineering
LINESTRING(-86.53345918188542 39.178792393330696,-86.5334861902633 39.17668616894187)
Lane shift on W 17th St
N Dunn south of E 17th St
August 21, 2023 to September 2, 2023
Duke Energy will be installing utility poles along N Dunn St south of E 17th St
Engineering
LINESTRING(-86.52834151153499 39.17893595581697,-86.5283169271173 39.17703973187403)
Intermittent Lane Restrictions On W 4th St and S Madison St for Duke Utility Work
W 4th St and S Madison St
August 21, 2023 to August 25, 2023
Duke Energy will have intermittent lane restrictions as they continue to their utility work along S Madison St and W 4th St.
Engineering
LINESTRING(-86.53683412457299 39.165613088198114,-86.53741949119859 39.16561791637454,-86.53742571850313 39.16603313830856,-86.53741949119859 39.16528477142265,-86.53741949119859 39.16562274455069,-86.5385964517543 39.16563722907699)
Intermittent Lane Restrictions On N Rogers for Duke Utility Work
N Rogers from app. E 3rd to app E 10th
August 21, 2023 to September 2, 2023
Duke Energy will have intermittent lane restrictions as they continue to their utility work along N Rogers St. It is possible that Duke Energy may conduct short duration (<1 hour) road closures to accommodate this work. Duke Energy will notify MCCSC, Transit, and emergency services if closures will be required
Engineering
LINESTRING(-86.53858141090913 39.17122946083768,-86.53865605815801 39.164863345399766)
Lane shift on W 17th St
W 17th in N Jackson St vicinity
August 21, 2023 to September 2, 2023
Duke Energy will be doing work along W 17th in preparation for additional utility work. This work will result in a lane shift while still allowing both east and westbound traffic to flow.
Engineering
LINESTRING(-86.53940225779925 39.17901594498295,-86.54005512537468 39.17901594498295)
Lane shift on W 17th St
W 17th between N College and N Walnut
August 21, 2023 to September 2, 2023
Duke Energy will be doing work along W 17th in preparation for additional utility work. This work will result in a lane shift while still allowing both east and westbound traffic to flow
Engineering
LINESTRING(-86.5346019336425 39.17898510714457,-86.53354148859779 39.17898275848222)
W Tapp Road
W Tapp Road from S Adams St to S Rockport Rd.
August 21, 2023 to August 31, 2023
Milling and resurfacing of W Tapp Road. Lane restrictions will be in place.
Street
LINESTRING(-86.54882081851788 39.136333052234505,-86.55403282380472 39.13650278256395,-86.55416212927939 39.13663393753828,-86.5543511142039 39.13671108740908,-86.55447047310359 39.136618507553976,-86.55461967172822 39.136487352550915,-86.55445057995367 39.13634848228136,-86.55429143475406 39.13627133201325,-86.55403282380472 39.13650278256395)
AEG Lane and Sidewalk Closure for Fiber Installation
1120 N Lincoln St
August 25, 2023 to July 13, 2024
BLN01a-F14_N Lincoln St, Underground and aerial fiber placement and excavations along alleyways and utility easements across N Washington St, N Lincoln St, N Grant St, N Dunn St between E 17th St and E 14th St.
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.53290382037741 39.178977203092415,-86.52832371153585 39.17900902930836,-86.52599936761439 39.17902518068135),LINESTRING(-86.52833065196364 39.17596521113089,-86.52834409169881 39.17733003592738,-86.52835658456175 39.17859868070346,-86.52835815974359 39.178758638106274,-86.52832377501868 39.179014518997775),LINESTRING(-86.53225051060403 39.17743657199739,-86.53169347806038 39.17743657199739,-86.53170035500538 39.17730862879654,-86.53100578356208 39.177329952679514,-86.53029745822883 39.17730329782478,-86.52835815974359 39.177329952679514),LINESTRING(-86.53291757426739 39.17857205770244,-86.5283512827986 39.178598712076166),LINESTRING(-86.53170035500538 39.17594921790885,-86.52835815974359 39.17596521113089),LINESTRING(-86.53096452189217 39.176866156765385,-86.53293820510233 39.17685549475436))
Lane Restriction on S Rogers
S Rogers St, adjacent to substation
August 28, 2023 to September 2, 2023
Duke Energy will be performing work on a pole on South Rogers, adjacent to the substation. There will be a short duration (<1 day) lane restriction with flaggers, while this work is performed
Engineering
LINESTRING(-86.53881040967119 39.15029208903263,-86.53881040967119 39.1470253381259)
W Country Club Drive
W Country Club Drive from S Rockport Road to S Madison St.
August 28, 2023 to September 14, 2023
Milling and resurfacing of W Country Club Drive.
Lane restrictions will be in place.
Street
LINESTRING(-86.54873048290236 39.13632124251515,-86.53413534105928 39.136005021973915)
Lane Restrictions on S Rogers St for Gas Work
Intersection of W 1st St and S Rogers St, primarily on the north, west, and south sides of the intersection
August 28, 2023 to September 1, 2023
Centerpoint and Miller Pipeline will be relocating gas piping on S Rogers St at W 1st St for the W 1st St Reconstruction project. S Rogers St will have shifting lane closures at the intersection to facilitate this work.
Engineering
LINESTRING(-86.53885558373926 39.15943019028589,-86.5385198268783 39.15943019028589,-86.53868495320336 39.15943445820582,-86.53868495320336 39.15956676359508,-86.53868495320336 39.159306420495426)
Lane restriction on E 17th St
E 17th St near Dunn St intersection
August 28, 2023 to September 2, 2023
Duke Energy will be installing poles along E 17th St, near the Dunn St intersection
Engineering
LINESTRING(-86.52740830040928 39.17901439495938,-86.52910890146745 39.1789868161882)
AEG Lane and Sidewalk Closure for Fiber Installation
714 N Morton St
September 1, 2023 to August 10, 2024
BLN01b-F10_N Morton St, Underground and aerial fiber placement and excavations along N Morton St, W 11th St, N Rogers St, N Madison St, N Jackson St, and nearby alleys and easements.
External Project
GEOMETRYCOLLECTION(LINESTRING(-86.53861055359397 39.17272997923786,-86.53858538426533 39.173263316193044),LINESTRING(-86.54104358869567 39.172834045302864,-86.54043113503214 39.17325030802277,-86.53859377404156 39.173269820277284,-86.53854343538427 39.17399176988883),LINESTRING(-86.53858538426533 39.173263316193044,-86.53720946096645 39.17327632436093),LINESTRING(-86.53481854768877 39.17327458102682,-86.53722641346182 39.173268076943),LINESTRING(-86.53933484311456 39.166626296082796,-86.53868978175473 39.16662089517399,-86.53664434390059 39.16660376932242),LINESTRING(-86.53866657657119 39.168591420975844,-86.53868982062485 39.16661810453442),LINESTRING(-86.53547051918957 39.16756422206595,-86.5397997241883 39.16760026438695),LINESTRING(-86.53860618145642 39.172730334122235,-86.53866681576898 39.16859364392988),LINESTRING(-86.53613492958017 39.17047000044434,-86.53608318661668 39.1716814561872,-86.53606430053912 39.17212362989653),LINESTRING(-86.5360891445321 39.17168160913141,-86.5366400510523 39.17168890988336,-86.5368189779563 39.17162685346753,-86.53727100381904 39.17125451382282,-86.53796787702409 39.171250863424376,-86.53839635987313 39.17140417999539,-86.53862708140724 39.17141513116624))
4th Streeet Festival of the Arts
4th Street between Lincoln & Indiana, Grant Street between Kirkwood and 3rd.
September 2, 2023 to September 3, 2023
4th Street Festival of the Arts
Public Works
GEOMETRYCOLLECTION(POINT(-86.53110517079966 39.16556232881237),POINT(-86.52694401996054 39.1655546472856),LINESTRING(-86.53111507830167 39.16556232881237,-86.53110517079966 39.16556232881237,-86.52981905225559 39.16555996026398,-86.52693411245853 39.1655546472856),LINESTRING(-86.52693411245853 39.1655546472856,-86.52693411245853 39.1655546472856,-86.52981899478496 39.165578719337105,-86.52979984828903 39.16660299885359,-86.52983814128089 39.16465833951233))
Road Closure for Gas Relocation Work on W 1st St
Intersection of W 1st St and S Rogers St on the east side of the intersection
September 4, 2023 to September 8, 2023
Centerpoint and Miller Pipeline will be relocating gas piping on W 1st St and S Rogers St for the W 1st St Reconstruction project. W 1st St just east of S Rogers St will be closed and all traffic will be detoured to W 2nd St or W Dodds St until construction is complete.
Engineering
LINESTRING(-86.53859080468624 39.15942312928368,-86.53636027452761 39.159402291509366)
Blue Ridge Neighborhood Picnic
E. Oliver Dr. from E. Ramble Rd. E to N. Ramble Rd. W
September 10, 2023 15:00 pm to 20:30 pm
Blue Ridge Neighborhood Picnic
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53378494168564 39.20296630811768,-86.53332294282379 39.202982102602135,-86.53295851669453 39.20299456133773,-86.53164595935571 39.20313582726746),LINESTRING(-86.53295851669453 39.20299456133773,-86.53333526926401 39.20297572585898),LINESTRING(-86.53333526926401 39.20297572585898,-86.53379709499434 39.20295689037516))