Allen St. Bridge
Bridge between S Morton and S Walnut (150-156 W Allen St)
January 7, 2020 to January 7, 2027
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
Planning & Transportation
LINESTRING(-86.53497807455625 39.15560747171148,-86.5349847800788 39.15559811226916)
B-Line Extension Project, from Adams St along Fountain, up Crescent Rd to 17th St.
Adams St along Fountain Dr., up Crescent Rd. to 17th St.
April 1, 2024 to November 15, 2024 daily until November 15, 2024
B-Line Extension Project. This project runs from Adams St along the north side of Fountain Dr., up the east side of Crescent Rd to 17th St. There will be lane restrictions throughout the project.
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.55154570965307 39.170728870443895,-86.55521901332583 39.17334679210555,-86.55670122308807 39.175225240685876),LINESTRING(-86.55673989032744 39.17525521592228,-86.55652078039554 39.17572481971655,-86.55659811290778 39.17904193408043))
Rolling Lane Closure for Fiber Installation - AT&T
W Country Club Dr at S Madison St; S Rogers St between W Ralston Dr and W Watson St
August 30, 2024 to December 31, 2024
Lineal will be working for AT&T to install fiber to connect to existing infrastructure for about 2 weeks between September and December 2024.
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.53768325285297 39.13604253720001,-86.53709024499783 39.13601780782696,-86.53722414999739 39.1371207294211),LINESTRING(-86.53911157284814 39.13840167945304,-86.53844842427895 39.13837695090854,-86.53828263713665 39.136799251816626))
Conduit installation along S Walnut St Pike and E Winslow Rd
S Walnut St Pike & E Winslow Rd; S Henderson St & E Winslow Rd
September 23, 2024 to December 27, 2024
Lineal will be installing conduit for AT&T to connect some of their existing infrastructure at the intersections of E Winslow Rd, S Walnut St Pike, and S Henderson St. The work is estimated to take about 7 days to complete and will include a lane and sidewalk closure at the locations. The work is planned between September 2024 and December 2024.
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.52873739116825 39.13589253529207,-86.52881526461753 39.13599488412237,-86.52887777603895 39.13607704257987),LINESTRING(-86.52880758360358 39.13599840018847,-86.52684219541364 39.13605889434348),LINESTRING(-86.52695179841065 39.13439149649986,-86.52678625012067 39.13439716166707))
Flock Safety Camera Installation Along E Kirkwood Ave and N Walnut St
Intersections of E Kirkwood Ave/ S Dunn St, E Kirkwood Ave/ S Grant St, W Kirkwood Ave/ N Walnut St, and N Walnut St/E 7th St
October 23, 2024 to February 23, 2025
Flock Safety is working with the Bloomington Police Department to install live video feed cameras in the right-of-way to aid in BPD investigations. The cameras will be placed in 4 locations along E Kirkwood Ave and N Walnut St. The installation will require a lane closure at each location and is expected to take 5 days to complete.
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.53357133571649 39.1686589718461,-86.53357444106325 39.1685795228299,-86.53346575392663 39.1685795228299),LINESTRING(-86.52827554433638 39.16662837741421,-86.52827554433638 39.16655735276254,-86.52846807583555 39.166564575611716),LINESTRING(-86.52991059769879 39.16653703479517,-86.5298158846226 39.1665334233692,-86.52981743729597 39.16644554528119),LINESTRING(-86.5335836883135 39.166679163000026,-86.5335836883135 39.16660452697732,-86.53343773701573 39.166608138399596))
AT&T Fiber Installation at the Intersection of S Madison St & W Smith Ave
W Smith Ave & S Madison St
October 24, 2024 to January 31, 2025
AT&T will be installing underground fiber at the intersection of S Madison St and W Smith Ave between October 14, 2024 and January 2025. When work begins the installation will require the temporary closure of W Smith Ave during day time hours and will not last more than 3 days once started.
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.53753840412124 39.16287163325691,-86.53741892384477 39.16286931726947,-86.5372392830538 39.1628658351396),LINESTRING(-86.53741127766757 39.162987595502756,-86.53741875569426 39.162874532315385))
Duke Energy Pole Removal
1798 S Rogers Street
November 20, 2024 to February 18, 2025
Single day lane closure adjacent to 1798 S Rogers Street to remove two temporary poles MNI-13983 and MNI-11785 and install a new anchor. Closure will occur in the date range of 11/20/24 to 02/18/2025.
Engineering
LINESTRING(-86.5388618439407 39.147853213148636,-86.5388343177871 39.148829638985575)
Duke N Fee Ln Lane Closure & Pole Installation
825 N Fee Lane
December 2, 2024 to March 15, 2025
Duke Energy will be installing new pole off of N Fee Ln. 1-2 day Lane restrictions only along N Fee Lane adjacent to 825 N Fee Lane in the date range of 12/2/24-3/15/25.
Engineering
LINESTRING(-86.51889218280641 39.17404346449811,-86.51891578629485 39.17426054630877)
620 S Park Ave Sewer Lateral Repair
620 S Park AVE
December 10, 2024 to December 12, 2024
Lane and sidewalk closure on E University St adjacent to 620 S Park Ave during working hours on 12/10/24 to repair a sewer lateral. The sidewalk and street will be excavated, the street cut will be plated overnight, and the removed sidewalk panel will be filled with crushed stone and compacted—sidewalk and pavement repairs to be completed on 12/11/24, with additional lane and sidewalk closures. The sidewalk and lane are to be reopened by 12/12/24.
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.52474839284405 39.16039181884136,-86.52403626635059 39.16038973910679),LINESTRING(-86.52473498179899 39.16042301485194,-86.52405370070919 39.1604178155178))
Duke Energy Lane and Sidewalk Closure
1200 W Grimes Ln
December 13, 2024 to January 3, 2025
Single-day closure of the northern lane and sidewalk of W Grimes Ln adjacent to 120 W Grimes Ln to Replace the riser on pole 761-710, install a new pad mount transformer and bore primary cable between new transformer and existing transformer 1D1. Work and closures will occur in the date range of 12/13/2024 to 01/03/2025
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.5356767315483 39.153388828260546,-86.53482305439523 39.15337562145396),LINESTRING(-86.5356767315483 39.15342019441627,-86.53482944100735 39.15340368591501))
Fiber Relocation for Broadview Learning Center at 705 W Coolidge Dr
705 W Coolidge Dr to W Graham Dr to S Rogers St and south to just past W Ralston Dr.
December 16, 2024 to May 16, 2025
Smithville has scheduled fiber relocation along W Graham Dr, S Rogers St, and just east of S Brown Ave for the Broadview Learning Center. The work is planned between 12/16/2024 and 5/16/2025, but will only take about a week to complete once work begins in the area. Temporary lane closures are expected and a sidewalk closure on S Rogers St for no more than 3 days is expected.
Engineering
LINESTRING(-86.54165863152343 39.14048866259188,-86.54160294424052 39.14016276545618,-86.54160800672078 39.13988005828523,-86.53865151824567 39.139805454814706,-86.53840547566134 39.137843542006095)
Utility Cabinet Install on east side of S Walnut St
S Walnut St just south of E Winslow Rd on the east side
December 16, 2024 to March 28, 2025
AT&T will be installing a utility cabinet on the east side of S Walnut St just south of E Winslow Rd that will take 2-3 days to install. The work is scheduled between 12/16/2024 and 3/28/2025. The work will primarily be on the road shoulder, but may include brief lane closures during the installation.
Engineering
LINESTRING(-86.53140196468983 39.134648252684315,-86.53139168876503 39.1347890677836,-86.53135058506582 39.134916598196554)
Residential Cable Connection Installation - 3148 S Coppertree Dr
3148 S Coppertree Dr
December 16, 2024 to January 16, 2025
Between 12/16/2024 and 1/16/2025, QC Communications will be installing a cable connection to the residence of 3148 S Coppertree Dr. The work is expected to take up to a day of work and will include boring underneath Coppertree Dr to the residence.
Engineering
LINESTRING(-86.50437633563978 39.13463022662313,-86.50431488161009 39.13467572763744)
AT&T Fiber Installation along S Woodscrest Dr and E 3rd St
S Woodscrest at E 2nd St intersection heading north towards 410 S Woodscrest; E 3rd St at S College Mall Rd intersection
December 16, 2024 to February 28, 2025
AT&T will be installing fiber along S Woodscrest Dr and E 3rd St between 12/16/2024 and 2/28/2025 for 2-3 days max once begun. The work will involve a short sidewalk closure and temporary lane closures for equipment
Engineering
GEOMETRYCOLLECTION(LINESTRING(-86.5000792424787 39.16421410144247,-86.49890808733562 39.16422524306569,-86.49871768481235 39.16416396411611,-86.49837998977111 39.16416396411611,-86.49830095476145 39.16380464556485),LINESTRING(-86.50295732782295 39.160970161846706,-86.50245507079751 39.16096242467813,-86.5024650494139 39.1618754046973,-86.50246837561937 39.16244278743983))
CBU Unscheduled Road Closure 12:45 pm today
617 S Fess Avenue both lanes between E 2nd St & E University St
December 18, 2024 12:44 pm to 16:45 pm daily for 10 times
CLOSING BOTH LANES AT 617 S FESS AVENUE BETWEEN E 2ND ST & E UNIVERSITY ST FOR APPROXIMATEL 4 HRS. TODAY 12/18 TO REPAIR A WATER SERVICE HIT.
Utilities
GEOMETRYCOLLECTION(LINESTRING(-86.52592115478065 39.161306985743636,-86.52592803729522 39.160389101220034),LINESTRING(-86.52592115478065 39.161306985743636,-86.52592115478065 39.161306985743636),LINESTRING(-86.52592115478065 39.161296312736596,-86.52591427226609 39.160394437792576,-86.52592115478065 39.1613016492403))