7/14/2016 09:33:01 Closed by Phil Peden
We have completed the installation of the storm sewer along Middle Ct and Parkway. Improvements in stormwater collection should be noticeable and should help alleviate the problem. There is still some roll curb to be installed this week, but the stormsewer work is complete.
6/17/2016 10:55:09 Phil Peden followed up on this ticket
CBU crews are finishing up the installation of the storm sewer. They began 2 weeks ago. We are still waiting on the roll curb contract to be approved before the project can be completed.
4/28/2016 09:51:07 Phil Peden followed up on this ticket
The proposals for roll curb are in and we've also ordered the precast structures. We will be working with the legal dept to get the proper documentation to hire the curb contractor. We will get started as soon as the structures arrive. Estimated start date is May 16.
3/29/2016 10:09:52 Phil Peden followed up on this ticket
We are currently in the process of seeking proposals for the roll curb replacement over the new storm pipe we will be installing. Once we have these numbers we can move forward with obtaining funding for this work.
3/17/2016 13:30:14 Nancy Axsom assigned this case to Phil Peden
Reassigned to Phil..He indicated this is at a standstill for now. We don't currently have the funding for the roll curb needed at this location.
3/10/2016 18:38:29 Anonymous assigned this case to Nancy Axsom
3/10/2016 18:38:29 Opened by Anonymous