7/27/2016 07:11:29 Closed by Danna Workman
Ron Arthur checked out..filled with asphalt, will keep a watch.
Other: There is a sinkhole developing in the northbound lane of fee road at the intersection with 10th st, near the manhole cover. There is currently a small hole in the asphalt, but there is a deeper hole that is roughly 2 feet deep below it, and the asphalt around the hole is starting to depress and cave in.
Most tickets of this type should be closed within 7 days, although some cases may be longer. 4 days have already passed.
Ron Arthur checked out..filled with asphalt, will keep a watch.
City | Bloomington |
---|---|
State | IN |
Latitude | 39.171619415283 |
Longitude | -86.518974304199 |
Status | Case Date | Category | |
---|---|---|---|
closed | 9/16/2016 | Potholes, Other Street Repair | |
closed | 9/16/2016 | Potholes, Other Street Repair | |
closed | 9/16/2016 | Potholes, Other Street Repair | |
closed | 10/11/2015 | Traffic Suggestions |