6/28/2018 13:46:47 Closed by Brandon Prince
CBU work on this issue is tentatively scheduled to begin on July 9, 2018
Other: Good morning Is this road ever going to be repaired? Someone made a big deal about this a while back, and we were told it is the city's responsibility and would be repaired after graduation. It is almost July and the situation keeps getting worse. As seen in the attached picture, the water is always there. It is constantly leaking from the sewer. The road in question is East 11th and Fee Ln.
Most tickets of this type should be closed within 7 days, although some cases may be longer. 2 days have already passed.
CBU work on this issue is tentatively scheduled to begin on July 9, 2018
This issue is at the top of our Storm repair list. Upon completion of the two current storm emergencies, CBU will begin working at this address. Projected timeline for completion is July 16-20, 2018
City | Bloomington |
---|---|
State | IN |
Latitude | 39.173301696777 |
Longitude | -86.51895904541 |