closed: Resolved #177927

Potholes, Other Street Repair:

Other: On the north side of the newly-paved 7th Street, between Dunn and College Avenues, there are numerous locations where sewer and water drain covers are sinking into the ground...it is excessively bumpy, hazardous and only going to get worse unless addressed immediately.

Assigned to
Roy Aten

Most tickets of this type should be closed within 7 days, although some cases may be longer. 34 days have already passed.

History

11/23/2021 08:56:05 Closed by Roy Aten

Castings adjusted by contractor.

Sent notification to Roy Aten, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=177927 Closed by Roy Aten Castings adjusted by contractor.

11/23/2021 08:55:45 Roy Aten contacted Anonymous

Michael, Thank you for reporting the issue with the castings. The contractor is adjusting the last casting this week. Thank you,

Sent notification to Roy Aten, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=177927 Roy Aten contacted Michael Bird Michael, Thank you for reporting the issue with the castings. The contractor is adjusting the last casting this week. Thank you,

10/25/2021 09:01:13 Roy Aten commented on this case.

Work continues on the project. Inlets that are out of grade on the north side of the roadway will be adjusted this week.

Sent notification to Roy Aten, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=177927 Roy Aten commented on this case. Work continues on the project. Inlets that are out of grade on the north side of the roadway will be adjusted this week.

10/21/2021 14:41:52 Roy Aten commented on this case.

Inlets on both the north and south side of the road are being adjusted to grade. The contractor begun this morning on the inlets on the south and they will progress to the inlets on the north within the next couple of days.

Sent notification to Roy Aten, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=177927 Roy Aten commented on this case. Inlets on both the north and south side of the road are being adjusted to grade. The contractor begun this morning on the inlets on the south and they will progress to the inlets on the north within the next couple of days.

10/20/2021 15:51:41 Neil Kopper assigned this case to Roy Aten

Sent notification to Roy Aten, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=177927 Neil Kopper assigned this case to Roy Aten You can use the link to follow progress on this case.

10/19/2021 12:36:13 Danna Workman assigned this case to Neil Kopper

Sent notification to Neil Kopper, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=177927 Danna Workman assigned this case to Neil Kopper You can use the link to follow progress on this case.

10/19/2021 12:25:56 Anonymous assigned this case to Danna Workman

Sent notification to Danna Workman, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=177927 Anonymous assigned this case to Danna Workman You can use the link to follow progress on this case.

10/19/2021 12:25:56 Opened by Anonymous