1/8/2024 12:50:49 Closed by Hank Duncan
Initial question answered by other City staff.
Sent notification to Hank Duncan, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Closed by Hank Duncan
Initial question answered by other City staff.
8/22/2023 11:16:02 Hank Duncan commented on this case.
Yes, they applied for the resident-led program. Results should be sent out by Wednesday of this week.
Sent notification to Hank Duncan, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Hank Duncan commented on this case.
Yes, they applied for the resident-led program. Results should be sent out by Wednesday of this week.
8/22/2023 10:18:33 Neil Kopper assigned this case to Hank Duncan
Hank, is this an area that submitted an application for traffic calming?
Sent notification to Hank Duncan, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Neil Kopper assigned this case to Hank Duncan
You can use the link to follow progress on this case.
Hank, is this an area that submitted an application for traffic calming?
8/22/2023 10:01:40 Alexandra Gray assigned this case to Neil Kopper
Do you have any information on speed reduction in the corridor?
Sent notification to Neil Kopper, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Alexandra Gray assigned this case to Neil Kopper
You can use the link to follow progress on this case.
Do you have any information on speed reduction in the corridor?
11/16/2022 07:36:22 Anonymous commented on this case.
I'll check with a colleague on the W 17th St plans. We had hoped to pave Lindbergh this year when 12th and 15th were paved. All of the utility work for BHA wasn't completed on Lindbergh in time for that to happen. The current plan is the pave in the spring. In the meantime, I'll be sure Snedegar Construction properly patches their utility cuts so it's as smooth as it can be.
Sent notification to Anonymous, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Paul Kehrberg commented on this case.
I'll check with a colleague on the W 17th St plans. We had hoped to pave Lindbergh this year when 12th and 15th were paved. All of the utility work for BHA wasn't completed on Lindbergh in time for that to happen. The current plan is the pave in the spring. In the meantime, I'll be sure Snedegar Construction properly patches their utility cuts so it's as smooth as it can be.
8/25/2022 20:00:35 Andrew Cibor assigned this case to Anonymous
Sent notification to Anonymous, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Andrew Cibor assigned this case to Paul Kehrberg
You can use the link to follow progress on this case.
8/25/2022 11:40:51 Anonymous assigned this case to Andrew Cibor
Sent notification to Andrew Cibor, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Chris Axsom assigned this case to Andrew Cibor
You can use the link to follow progress on this case.
8/25/2022 11:40:41 Opened by Anonymous
!
Sent notification to Danna Workman, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Opened by Chris Axsom
!
8/25/2022 11:33:15 Closed by Anonymous
Sharon, The first part of your question needs to go to Utilities because that is their project and can not be paved until project is completed. The second question would be addressed by City Engineering.
Sent notification to Danna Workman, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Closed by Chris Axsom
Sharon, The first part of your question needs to go to Utilities because that is their project and can not be paved until project is completed. The second question would be addressed by City Engineering.
8/25/2022 08:43:54 Anonymous assigned this case to Danna Workman
Sent notification to Danna Workman, Anonymous
https://bloomington.in.gov/crm/tickets/view?ticket_id=181192
Anonymous assigned this case to Danna Workman
You can use the link to follow progress on this case.