Choose types

Allen St. Bridge

Bridge between S Morton and S Walnut (150-156 W Allen St)

January 7, 2020 to January 7, 2027
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
Planning & Transportation
LINESTRING(-86.53497807455625 39.15560747171148,-86.5349847800788 39.15559811226916)

E Gilbert Dr

E Gilbert Dr from N Walnut St to N Lavern Dr

May 1, 2021 to September 1, 2021 daily until September 1, 2021
E Gilbert Dr will be closed for sanitary sewer replacement.
Planning & Transportation
LINESTRING(-86.53331652707108 39.189363110139965,-86.53298272283654 39.18936728302555,-86.53242279315278 39.18920871319881)

7-Line, 7th Street Protected Bike Lane

7th Street from the B-Line Trail to North Indiana Avenue.

June 1, 2021 to October 30, 2021
Eastbound lane closed to through traffic.
Planning & Transportation
LINESTRING(-86.53697688912268 39.168565471661935,-86.52705066426013 39.16851254375996)

Discovery Parkway

East Discovery Parkway from IU Hospital to Old Range Road.

June 28, 2021 to October 30, 2021
Multi-use trail construction. Westbound lane closed to through traffic.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.50080631205216 39.175586339267625,-86.50016470468856 39.17550344207967),LINESTRING(-86.50016470468856 39.17550344207967,-86.50002212527441 39.1755089685619,-86.49965141879764 39.17544265074639,-86.49929497026231 39.17542607128274,-86.4989599086391 39.17543159777108,-86.4988601030492 39.17537633286835,-86.49836820407042 39.175475809661975,-86.49819710877345 39.17553660096658,-86.49665012213008 39.175851609612295,-86.49627228668263 39.17584608315701,-86.49600851476647 39.17576318627525,-86.49586593535233 39.175669236357834))

South Olcott Blvd

South Olcott Blvd from East Moores Pike to East Winston Place

October 4, 2021 to October 28, 2021
Milling/Paving, weather permitting, 6:00 am to 4:00 pm
Street
LINESTRING(-86.48495560430314 39.15016706280082,-86.48490726159935 39.14997336692886,-86.48483071898501 39.149767173963255,-86.48483474754367 39.14962346335727,-86.48490726159935 39.149298551340195,-86.48489114736473 39.149061114686816,-86.4847420906947 39.1488049321361,-86.48446814870654 39.148598735747214,-86.48429492068462 39.14843627756082,-86.48418212104244 39.148276943206014,-86.4841378068973 39.148017633582924,-86.4841458640146 39.14789578897228,-86.48418212104244 39.14770521108133,-86.48443994879601 39.14740528417505,-86.48543097422395 39.146880409013704,-86.48560017368722 39.146736692513116,-86.48569283053617 39.146586727156176,-86.4857049162121 39.145786906522716)

Lane Closure on N Walnut

1800 North Walnut

October 28, 2021 to December 1, 2021
CenterPoint Energy (through Miller Pipeline) will be closing the eastern most lane at approximately 1800 N Walnut daily to perform natural gas work. It is anticipated that the lane will open each afternoon after work has been completed, and remain open on weekends. Wright Traffic Control will be setting up all signage, barricades, and an arrowboard.
Planning & Transportation
LINESTRING(-86.533988814937 39.18303537795694,-86.53368425852737 39.18157600677213)

Lane Restriction - Fire Hydrant Installation

500 Block of N Woodlawn between 9th St. and 10th St.

November 2, 2021
Please be advised that CBU crews have closed one lane on the 500 block of N. Woodlawn between 9th St. and 10th St. for a fire hydrant installation. Normal traffic flow is expected to resume at 4:00pm. We will be flagging.
Utilities
LINESTRING(-86.52348407756588 39.17164507226471,-86.52346368335724 39.17043215090328)