6/30/2025 08:51:59 Closed by Roy Aten
Answered the question with thorough comments, work will begin as soon as the area dries out. The project is scheduled for completion this year.
Other: When will the B-Line trail be finished between Adams Street and Fountain Drive? There has been no activity or progress on this "missing link" since 2024. What is the hold-up or reason for delay? Please provide a timeline for completion of this last section. Thank you.
Answered the question with thorough comments, work will begin as soon as the area dries out. The project is scheduled for completion this year.
The project is scheduled for completion this year. The project was delayed by a few months due to some environmental concerns in the Adams Street area. Remediation and final work will begin as soon as the weather allows for more grading work to take place.
City | Bloomington |
---|---|
State | IN |
Zip | 47404 |
Latitude | 39.170845031738 |
Longitude | -86.55004119873 |
Township | Bloomington |