open #192640

Utility Construction Projects

1403 W 8th ST

Case Date:
8/2/2024

A rubber boot is on the ground by the power pole. It appears to be an insulator.

open #192653

Utility Construction Projects

2602 N Kinser PIKE

Case Date:
8/3/2024

Tree fallen on power (internet?) lines

open #192654

Utility Construction Projects

2602 N Kinser PIKE

Case Date:
8/3/2024

Tree fallen on power (internet?) lines

open #193323

Utility Construction Projects

819 N Indiana Ave

Case Date:
9/3/2024

Fiber optic installation created some cylindrical holes in the concrete and asphalt about 6" in diameter in various locations. At this intersection, there is one that was apparently refilled with gravel, but another was left open and a stepping hazard. It is on the north part of the intersection, just north of where 11th crosses and closer to the east side of the street than the west. We found a concrete core by the side of the road that likely came out of the hole originally so we placed it back in the hole, but it sunk down a ways because it was unsupported beneath and now it needs to be topped off with gravel or the core should be removed and the entire hole filled with gravel.

closed #179529

Utility Construction Projects

E Winslow Farm Dr, Bloomington, IN 47401, USA

Case Date:
4/13/2022

Reported by Joanne Freeman to me. Unfinished AT&T fiber project started last summer has left exposed conduit, foot-deep holes and sand fill in rights of way (meaning grass doesn't grow). She wants City inspectors to contact Michael or Sharon Dalton who are the property managers for the subdivision to get this situation addressed. AT&T has been unresponsive to neighborhood contact. Pegasus contact info is (812) 824-3239 and pegasus.properties.gmail.com. They can provide more detailed information.

closed #179592

Utility Construction Projects

Case Date:
4/21/2022

The electrical poll is damaged and looks to be falling.The poll is on Hillside Drive Bloomington Indiana.

closed #179861

Utility Construction Projects

316 E Cottage Grove AVE

Case Date:
5/14/2022

Att box knocke I Br

closed #180579

Utility Construction Projects

3857 S Mill Stone WAY

Case Date:
7/11/2022

2 things: (1) large city tree at SE corner of Sare and Mill Stone Way severely damaged, broken and dangling branches causing hazard for drivers -dangerous, needs immediate attention; (2) damage caused by water main being hit during Smithville contractor work, the same corner is in disarray, lawns torn up, streets are a mess, and city drain affected.

closed #181002

Utility Construction Projects

3304 E Winston ST

Case Date:
8/12/2022

AT&T left large holes in ground after installing high speed internet.

closed #181095

Utility Construction Projects

2200 E Moores Pike, Bloomington, IN 47401, USA

Case Date:
8/18/2022

AT&T lines need to be resupported. They were sagging and a truck snagged them. It broke a power pole that Duke replaced but the AT&T lines are just temporarily tied up. The whole line is a mess from High Street east with broken poles and sagging lines.