7/14/2017 13:35:29 Closed by Phil Peden
This issue is noted. We have a project in our capital improvement plan to improve High St drainage from Nancy to 2nd St. I am not sure when the project will be designed and constructed.
Other: Can you please look at the drainage on High Street in this area? The street is always covered in water with medium to heavy rains. It doesn't appear that there are enough drains on this area of the street. This has been a problem for years.
Most tickets of this type should be closed within 7 days, although some cases may be longer. 71 days have already passed.
This issue is noted. We have a project in our capital improvement plan to improve High St drainage from Nancy to 2nd St. I am not sure when the project will be designed and constructed.
I drove by during a rain event and observed storm water encroaching into the northbound lane through this section of road, near the 939 address. There is not much that can be done here. There is new curb and sidewalk, an inlet would have helped but there isn't storm sewer in the area. CBU and the Transportation department are looking at a long term solution for High St between Covenanter and Maxwell that would include storm sewer, inlets, curb, and sidewalk.