3625 E Morningside DR
- Case Date:
- 2/26/2019
the western end of Morningside Drive--west of Smith Road--has long been unsafe because there are no sidewalks. There are several families with young children, many residents walking dogs and walking to the park, and sidewalks would greatly improve general safety. thanks.
City Construction Projects
720 W 7th ST
- Case Date:
- 9/9/2019
I may have sent this to the wrong department earlier today. Cars are parking regularly in front of the hydrant on the North East corner of Maple Street at West 7th. Can you please come and repaint the curb? You guys did a great job repainting the curbs on W 7th but the curbs on Maple need it too. Thanks.
City Construction Projects
600 W 6th ST
- Case Date:
- 9/12/2019
I feel like the city should know that I broke my foot walking down the horrible Near West Side sidewalk last week.
City Construction Projects
301-399 S Mitchell St, Bloomington, Indiana, 47401
- Case Date:
- 10/10/2019
Was pulling to side of road to park I hit this drain. It broke the right leaf spring on my cargo trailer.
City Construction Projects
Bloomington, Indiana
- Case Date:
- 11/2/2019
Olcott park pathway to Jackson Creek middle school parking lot. When the temperature drops below freezing, this becomes a sheet of ice due to some drainage from the football field flowing down the paved path. Dozens of school children use the path to get to and from school as well as community members. It has been a high slip risk For the last few years as this path does not receive ice removal or salting on a regular basis. Instead of trying to keep up with salting or removing the ice on this long path I hope the city could look into rerouting the source of the drainage to not flow on the pedestrian path.
City Construction Projects
3073-3099 E Moores Pike, Bloomington, Indiana, 47401
- Case Date:
- 12/6/2019
Road striping/painting contractor created a major hazard and delay yesterday at E. Moores Pike/College Mall Rd/S Sare Rd.
City Construction Projects
301 E Winslow RD
- Case Date:
- 12/9/2019
The sidewalk widening project along S. Henderson St. is extremely dangerous for pedestrians and a hazard for vehicles pulling in and out of Winslow Plaza as well. The contractor dug 2' deep x 2' footings for new curbs at the sidewalks crossing the entrances to Winslow Plaza and put up now warning signs, barricades, cones, or caution tape. No sidewalk closed signs have been put up. Who is supervising this project?
City Construction Projects
4612 W Arlington RD
- Case Date:
- 11/15/2018
Where the new water line is going in on Arlington/17th there is cut actoss the road at the 46 bridge. It has been pretty deep to drive across but today on my way home the west bound lane has ~6inch drop towards the shoulder. Even slowing down I was afraid I damaged my car because you cant see the drop until you have already drove across it. Im in a bigger vechicle and it was a huge jar...
City Construction Projects
2907 S McIntyre Dr, Bloomington, Indiana, 47403
- Case Date:
- 11/19/2018
New Island in the middle of Tapp road just east of Kegg is not marked with any traffic cones or signs, hazardous, difficult to see
City Construction Projects
1010 W 7th ST
- Case Date:
- 12/7/2018
The manhole cover for the sewer on W 7th Street close to Elm is not secured. I stepped on it and it moved under me and I almost fell in the hole.