City Construction Projects
1103 N Woodburn AVE
- Case Date:
- 1/22/2003
Letter stated Mr. Schatz feels that a crack (leak) in his pvc pipe connector to meter was caused by damage during construction. Customer had break repaired but received extra large water bill. Wants matter investigated and adjustment made.
City Construction Projects
420 E Kirkwood AVE
- Case Date:
- 6/13/2000
Mr. Koontz called T&D and said that his wife was driving on the alleys at 420 E. Kirkwood (behind McDonalds's) and did a lot of damage to her car.
City Construction Projects
309 N Walnut ST
- Case Date:
- 6/16/1999
sidewalk torn up in the 300 block, in front of Taco Bell (think by gas company) and was never repaired. Has been out for awhile and is a hazard to pedestrians (Carol I also think they did not repair the sidewalk next to Alice's house on Morton and 10th. You may want to address both of these walks with them)
City Construction Projects
401 N Morton ST
- Case Date:
- 5/25/2005
citizen querried in re plans for improvement for three locations: rodgers rd between sare and snoody, olcott in hyde park, and generally potholes throughout the city. said they were "aweful".
City Construction Projects
401 N Morton ST
- Case Date:
- 8/12/1996
Says promised traffic calming devices have not been installed. Were told they'd go in right away (6th St). Says City Landscaper told him no one discussed watering of greenery with him. Says City departments aren't coordinating and work isn't getting done.
City Construction Projects
401 N Morton ST
- Case Date:
- 8/9/1996
Sidewalk on Maple from 5th to 6th was recently replaced. While it needed to be replaced, this was a historic sidewalk as are many on the west side. Policy should be developed to preserve historic sidewalks in original condition when repairing/replacing.
City Construction Projects
401 N Morton ST
- Case Date:
- 8/9/1996
She's at Walnut & Wylie. Why hasn't anything been done about Wylie Street in a month or more? She's losing business and Wylie Street residents are using her parking lot.
City Construction Projects
401 N Morton ST
- Case Date:
- 6/10/2003
City Construction Projects
110 S Clark ST
- Case Date:
- 9/19/2001
Ms. Ritter stated that a street cut was done in front of her house and that the street cut has fallen in. She thought that the cut was made to repair a gas line, but said that the City made the cut?
City Construction Projects
423 E Kirkwood AVE
- Case Date:
- 7/2/1998
Mr. Madsen called to express his concern about the efficiency of tax money on the sidewalk sweeper the City just purchased. He believes the City merchants should sweep their own sidewalks, and in the winter should shovel their own walks to better promote people to use the dowtown area. This was just a general complaint to voice his concern.