Utilities Construction
7046 S Shields Ridge RD
- Case Date:
- 9/4/2013
Resident (Shawn Waylen?) at 7046 S. Shields Ridge Rd. reports that repairs are needed to yard and driveway. The new 36" water transmission pipeline was installed in this area.
Utilities Construction
6000 S Handy RD
- Case Date:
- 8/28/2013
Received voice message from James Eller, owner and resident of 6000 S. Handy Rd. Mr. Eller alleges that settlement occurred to his yard as a result of CBU's water transmission main project.
Utilities Construction
4674 W Gifford RD
- Case Date:
- 8/9/2013
Water standing and running down the street in front of his residence
Utilities Construction
S Walnut Street PIKE
- Case Date:
- 8/9/2013
Heavy rain water is not going into the storm drain properly