This project will replace the signals and crosswalks at the intersections of 11th & Walnut and 14th & Walnut.

Project Timeline:

  • Design: Fall 2020
  • Construction: 2022

Maintenance of Traffic:

Construction Progress:

Bidding Documents:

Letting Date: November 17th, 2021 at 11:45 AM

 

 

Zoom meeting link for Bid Opening- Click here for meeting

 

 

 

Bid Results:

Ragle Inc.- $761,956.75

E&B Paving, LLC- $958,000.00

 

Bids are due in the City Hall Atrium by 11:45 AM on November 17th, 2021.  Bids will be opened and read aloud at a virtual meeting, City Hall, 401 North Morton Street at 12:00 PM (Noon) on November 17th, 202