Project Details:

This project will construct a sidewalk on the west side of Adams Street from Kirkwood Ave to Fountain Drive, including accessible curb ramps. The project was programmed through the Council Sidewalk Committee and has received additional funding support with a Community Development Block Grant of $140,000.

Project Timeline:

  • Design: 2021
  • ROW Acquisition: 2023
  • Project Bidding (TBD) 2023
  • Construction: Start date of March 18th 2024 through Mid-June 2024. The southbound lane of Adams St will be closed for a total of 60 days through this project. The project is scheduled for a total of 90 days.

 

Bidding Documents:

The letting date for this project is on December 4th, 2023 at noon. Awarding will be announced at the Board of Public Works session on December 5th, 2023 at 5:30PM. To view all bidding documents, please go through OpenGov. 

https://bloomington.in.gov/engineering/bids

Plans

Bidding Packet

Addendum #1

Addendum #2

Invitation to Bidders

City Procurement Portal

(Disclaimer; all documents are for reference only. Official documents are located on OpenGov.)

Bids opened 12-4-2023

Crider & Crider $369,683.00

E&B Paving      $456,654.00

Milestone          $511,500.00

River Town        $608,776.37

 

Project Contact:

Jason Kerr, Project Manager

Engineering Department 812-349-3913