This project will mill, repave, and replace pavement markings on two City streets;

  • North Arlington Road, from just north of the round-a-bout on West 17th Street to the I69 overpass.
  • West Bloomfield Road, from South Adams Street to South Basswood Drive.

Project Timeline:

  • Bid, November 2019
  • Construction: Spring 2020

Bidding Documents

Letting Date: November 20th, 2:00 PM

Invitation to Bidders

Bid Packet

Addendum #1

Bidding (Closed)

Bids were opened November 20th, 2019 by 2:00PM.

  • E&B Paving, Inc
    • Arlington Base Bid $236,660.54
    • Bloomfield Base Bid $345,831.88
      • Total Bid $582,492.42 (awarded)
  • Milestone Contractors, LP
    • Arlington Base Bid $265,076.40
    • Bloomfield Base Bid $345,868.40
      • Total Bid $610,944.80

Project Contact:

Roy Aten
(812) 349-3423 or atenro@bloomington.in.gov