Page last updated on September 26, 2024 at 11:18 am
This project will construct improved crosswalks at up to 10 locations throughout the City. Additional location information will be available as the project progresses. Design and construction is federally funded with a local match. This project utilizes funding from the Highway Safety Improvement Program (HSIP).
A design consultant has yet to be selected. Project scoping should be complete by the end of 2024. Design and right-of-way acquisition (if required) will take place during 2025 and 2026. The project will be bid out for construction in mid-2027. Construction will begin late 2027 and should be complete by mid 2028.
Project Timeline:
- Design: 2025/2026
- Construction: Mid 2027 - Mid 2028
Public Input:
The public can provide feedback or ask questions regarding this project by reaching out to the project contact below.
Kendall Knoke
(812) 349-3467 or kendall.knoke@bloomington.in.gov