This project will improve crosswalks and curb ramps at 15 different locations throughout the downtown area.  The goals of the project will include improvements to pedestrian safety at intersections and provide a continuous ADA compliant route along 6th Street from Rogers Street to Indiana Avenue, and also along Washington Street from 9th Street to 2nd Street.

Project Timeline:

  • Design: 2018
  • Construction: May 2019 thru July 2019 (construction is substantially complete)

Bidding Documents

Letting Date: March 19th, 2019

Bidding Results

  • Groomer Construction Inc,   $461,081.04 Award
  • Milestone Contractors, LP,   $466,500.00
  • E&B Paving, Inc,                 $617,900.00

Project Contact:

Roy Aten