This project is listed as a high priority bicycle network connection in the City's Transportation Plan. The project provides a connection for the east-west Smith/Hunter neighborhood greenway (currently it is not feasible for bicyclists to make this connection when travelling eastbound due to the one-way configuration of Henderson).

Construction is planned to occur during the summer of 2023.

Project Timeline:

  • Design: 2022
  • Construction: 2023

Henderson St Greenway project completed on 7-12-2023, at a final cost of $191,580.93, work performed by Rivertown Construction.

Bidding Documents:

Letting Date: November 3rd, 2022, 12:00 PM  

 

Award Date: November 7th, 2022

Zoom meeting link for Bid Opening- LINK

No pre-Bid meeting was scheduled for this project.

 

Bid (Open):

Rivertown Construction, LLC: $193,994.54 (Awarded)

E&B Paving, LLC:                      $212,500.00

Milestone Contractors, LP:     $225,500.00

Crider & Crider, Inc.:               $346,772.25

 

Project Contacts:

Neil Kopper, Project Engineer

812.349.3913 or koppern@bloomington.in.gov

 

Jason Kerr, Project Manager

812.349.3913 or kerrja@bloomington.in.gov