This project will clear a portion of the trees along the upcoming Jackson Creek Trail Phase II Project. This advanced work is required as a part of upcoming utility relocations that will be performed this spring. Tree removal work is anticipated to begin in March and completed in April.
Project Timeline:
- Design: Complete
- Construction: Winter 2020
Maintenance of Traffic:
- Some sidewalks will have intermittent closures with pedestrian detours or walk-arounds in place.
- Traffic may be reduced to one lane depending on the location of the work.
Construction Progress
Quote Documents
Letting Date: (Closed) March 15th, 2021, 11:30 AM
Quotes
- Bluestone Tree, $56,890.00
- Monroe LLC, $68,500.00