This project will install a sidewalk on the west side of S Walnut Street from approximately 650 feet south of Burks Drive to 1,000 feet north of Burks Drive.
Project Map:
Project Description:
Funding for design and construction is provided through the Common Council Sidewalk Committee. This project would install a sidewalk on the west side of S Walnut Street from approximately 650 feet south of Burks Drive to 1,000 feet north of Burks Drive.
The Etica Group has been selected as the engineering consultant for this project.
Project Timeline:
- Design: 2017
- Construction: spring 2019
Quote Documents:
Quote Results:
-
Milestone Contractors, LP $147,525.00
-
E&B Paving, Inc. $119,439.00 (Awarded)
Project Contact:
- Russell White
- (812) 349-3423 or whiter@bloomington.in.gov