Skip to main content

Page last updated on September 23, 2024 at 8:09 am

Project Information

This maintenance project will include asphalt resurfacing and pedestrian accessibility improvements on West 3rd Street from Franklin Road to Patterson Drive. Construction funding is provided in part by the Community Crossings Matching Grant program.

Project Timeline

1. Bids to be advertised June 24, 2024

2. Bid Submission Deadline July 15, 2024 at 12:00 pm local time

3. Tentative Bid award July 30, 2024

4. Construction to be completed in 2024.

5. Construction starting late September and going through late November, 2024.

Bid Information

Bids: Received July 15, 2024

E&B Paving      $1,060,200.00 Awarded 7-30-24

Milestone         $1,127,922.55

https://procurement.opengov.com/portal/bloomingtonin

Plans

Plan Set 

For More Information

Contact Project Manager Jason Kerr

kerrja@bloomington.in.gov

812-349-3913