This project will replace the signals and crosswalks at the intersections of 11th & Walnut and 14th & Walnut.
Project Timeline:
- Design: Fall 2020
- Construction: 2022
Maintenance of Traffic:
Construction Progress:
Bidding Documents:
Letting Date: November 17th, 2021 at 11:45 AM
Zoom meeting link for Bid Opening- Click here for meeting
Bid Results:
Ragle Inc.- $761,956.75
E&B Paving, LLC- $958,000.00
Bids are due in the City Hall Atrium by 11:45 AM on November 17th, 2021. Bids will be opened and read aloud at a virtual meeting, City Hall, 401 North Morton Street at 12:00 PM (Noon) on November 17th, 202
Project Contact:
Matt Smethurst
(812) 349-3514 or smethurm@bloomington.in.gov