This project is listed as a high priority bicycle network connection in the City's Transportation Plan. The project provides a connection for the east-west Smith/Hunter neighborhood greenway (currently it is not feasible for bicyclists to make this connection when travelling eastbound due to the one-way configuration of Henderson).
Construction is planned to occur during the summer of 2023.
Project Timeline:
- Design: 2022
- Construction: 2023
Henderson St Greenway project completed on 7-12-2023, at a final cost of $191,580.93, work performed by Rivertown Construction.
Bidding Documents:
Letting Date: November 3rd, 2022, 12:00 PM
Award Date: November 7th, 2022
Zoom meeting link for Bid Opening- LINK
No pre-Bid meeting was scheduled for this project.
Bid (Open):
Rivertown Construction, LLC: $193,994.54 (Awarded)
E&B Paving, LLC: $212,500.00
Milestone Contractors, LP: $225,500.00
Crider & Crider, Inc.: $346,772.25