Page last updated on October 29, 2026 at 1:45 pm
Project Summary:
This project will replace the existing traffic signal equipment and make intersection geometry improvements at the intersection of Grimes Lane and Walnut Street. Kimley-Horn & Associates Inc. is the engineering design consultant for this project.
Project Timeline:
- Design: 2025
- Construction: 2027
Bid and Award Information:
- Advertisement/Release Date: October 28th, 2026
- City's Procurement Portal
- Letting Date: 1:30 pm local time on Wednesday, 18th, 2026
- Anticipated Award Date: 5:30 pm on Tuesday, 15th, 2026, in the Council Chambers of City Hall at the Showers Building, 401 N. Morton Street, Bloomington, Indiana, and via Zoom by using the following link: https://bloomington.in.gov/boards/public-works.
Project Contact:
- Neil Kopper, Senior Project Engineer, [email protected]
- Zac Rogers, Project Manager, [email protected]