This maintenance project will include asphalt maintenance, accessible sidewalk curb ramps, minor curb modifications, and restriping. It will also include median island installation at the intersection of Overhill and 3rd to address crash trends.

Construction funding is provided by the Community Crossings Matching Grant program.

 

Project Timeline:

  • Design: Spring 2023
  • Construction: Summer/Fall 2023.

 

Bidding Documents:

Letting Date: May 22nd, 2023

 

Zoom meeting link for Bid Opening- 

 

Bids are due in the City Hall Atrium by 11:45 AM on Monday, May 22nd, 2023.  Bids will be opened and read aloud at a work session of the Board of Public Works, in the Council Chambers, City Hall, 401 North Morton Street at 12:00 PM (Noon) on Monday, May 22nd, 2023. 

 

Bid Results: 

E & B Paving, LLC- $946,815.00

Milestone Contractors, LP- $958,859.00

 

 