This project is a part of the City's Recover Forward initiative.  It will replace the sidewalks on West 6th Street from North Elm Street to North Fairview Street.  In addition, it will also replace the eastern sidewalk on North Elm Street from West 4th Street to West 5th Street.

Project Timeline:

  • Design: Fall 2020
  • Construction: Spring 2021

Maintenance of Traffic:

Construction Progress

Bidding Documents

 

Bids are due in the City Hall Atrium by 11:30 AM on Monday, December 7th, 2020.  Bids will be opened during a Board of Public Works work session virtual meeting at 12:00 PM (Noon) on Monday, December 7th, 2020.  For those interested in joining the opening meeting please email workmand@bloomington.in.gov or follow this link at the time of the meeting.

Letting Date:

December 7, 2020

Bid Opening:

December 7th, 2020 Board of Public Works or subsequent meeting

No pre-bid meeting is scheduled for this project.

Results:

CGR, LLC  $ 178,160.00

River Town Construction LLC $ 249,250.00 (Award)

Milestone Contractors, L.P $ 316,300.00

Groomer Construction, INC $ 355,932.81

Crider & Crider, INC $ 397,500.00

 

Project Contact:

Joe Vandevender
(812) 349-3448 or vandevej@bloomington.in.gov