This project will provide asphalt resurfacing on North Walnut Street from the SR 45 Bypass to 400 feet north of N Old 37. The project will also include curb ramp replacements, curb repair, guardrail repair, removal of excess pavement, and updates to signs and markings.

In order to improve safety at the intersection of Walnut Street at Blue Ridge Drive, a left turn lane will be installed for use by southbound traffic to turn into the the Blue Ridge Neighborhood. Walnut Street will also be modified to include a single southbound travel lane throughout the project limits to replace the current configuration which opens from one lanes to two lanes and then merges back down to one lane.

Up to 50% of project funding is provided by the Community Crossings Matching Grant program.

Project Timeline:

  • Design: 2025
  • Construction: TBD, late 2025

Project Documents:

Bid and Award Information:

  • Advertisement/Release Project Date: May 19, 2025
  • Pre-Bid Conference (Non-Mandatory): May 22, 2025, 10:30 am

    401 N Morton ST STE 135
    Bloomington IN 47404
    McCloskey Conference Room

  • City's Procurement Portal
  • Letting Date: 12:00 pm local time on Monday, June 2nd, 2025
  • Award Date:  5:30 pm on Monday, June 3rd, 2025, in the Council Chambers of City Hall at the Showers Building, 401 N. Morton Street, Bloomington, Indiana, and via Zoom by using the following link: https://bloomington.in.gov/boards/public-works.

 

Project Contact:

Neil Kopper, Senior Project Engineer, koppern@bloomington.in.gov

Zac Rogers, Project Manager, zac.rogers@bloomington.in.gov