This project will include installation of traffic calming devices along E Maxwell Ln from Henderson St to Woodlawn Ave. Traffic Calming devices include speed humps, pavement markings, and signs. 

This traffic calming project was prioritized through the City's Resident-Led Process of the Traffic Calming and Greenways Program (TCGP). For additional information on this prioritization process, please contact the Planning and Transportation Department at 812-349-3913.

Project Timeline:

  • Design: Fall 2022
  • Construction: Spring/Summer 2023
  • Construction Completion, May 5th, 2023

Quote Documents:

 

Letting Date: December 5, 2022

Award Date:  December 6, 2022

Quote (Open):

E&B Paving, LLC: $36,900.00 (Awarded)

Milestone Contractors, LP: $98,851.00

No pre-Quote meeting is scheduled for this project.

Quotes are due in the City Hall Atrium by 11:30 AM on Monday, December 5th, 2022.  Bids will be opened and read aloud at a virtual meeting, City Hall, 401 North Morton Street at 12:00 PM (Noon) on Monday, December 5th, 2022.

Results:

E&B Paving, LLC: $36,900.00 (Awarded)

Project Contacts:

  • For questions related to the traffic calming process and project prioritization:
    • Hank Duncan, Bicycle and Pedestrian Coordinator
    • (812) 349-3529 or hank.duncan@bloomington.in.gov
  • For questions related to coordination during construction:
    • Roy Aten, Senior Project Manager
    • (812) 349-3913 or atenro@bloomington.in.gov
  • For questions related to project design:
    • Neil Kopper, Project Engineer
    • (812) 349-3593 or koppern@bloomington.in.gov