Hunters Creek Road, Phase I 2.85 miles east of SR 446 April 2, 2018 to October 1, 2018
This project is phase one of three phases. The road is being reconstructed. The improvements will include 2-10' paved lanes and a 2' aggregate shoulder with improved drainage facilities. For further information or questions please contact the department at 812.349.2555.
Monroe County Highway Department
LINESTRING(-86.33120759367742 39.00781679185715,-86.32992013335027 39.00921738565552,-86.32946662365637 39.01039894697425,-86.32989577709874 39.01126595284833,-86.32938079296788 39.01279986028186,-86.32775000988684 39.01573419919441)
Rhorer Road Old SR 37 South to Walnut St Pike May 1, 2018 to October 1, 2018
This project is part of the Fullerton Pike Corridor, Phase I. Rhorer Road will be closed for approximately 150 days for the road reconstruction. The intersection of Walnut Street Pike and Rhorer will have restricted lane movements through out the project. The detour route is Old SR 37 South to Fairfax Road. Gordon Pike will remain open during this duration but with construction along the corridor. For further information or questions please contact the department at 812.349.2555.
Monroe County Highway Department
LINESTRING(-86.53135322099078 39.121437233312264,-86.52666471963273 39.12144971862483)
Fullerton Pike, Phase I Rhorer Road May 7, 2018 to November 29, 2018
This segment of Rhorer Road is to be closed for the road reconstruction project and signal installation. Detour routes are posted for this closure.
Monroe County Highway Department
LINESTRING(-86.53135528781597 39.12145920805793,-86.52659168460553 39.12142591389073)
Vectren-Miller Gas main replacement Downtown-various locations May 7, 2018 to September 1, 2018
Miller Pipeline will have one day one lane closures in 7 locations (as shown on the map and listed below) over the course of this project. Flaggers and signage will be in place. Each segment will be updated with a specific date and time when that is determined over the course of the project. Washington St (between 4th and Kirkwood) Lincoln St (between 4th and Kirkwood) Grant St (between 4th and Kirkwood) Lincoln St (between 6th and 7th) Sixth St (between Walnut and Washington) E Kirkwood Ave (between Walnut and S Washington St) E Fourth St (between Walnut and S Washington St)
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.53334595037083 39.16559640665622,-86.53295703006368 39.16559224749483),LINESTRING(-86.53233475757219 39.16634089258267,-86.53234012199023 39.165937457053104),LINESTRING(-86.53107948375322 39.166365847281696,-86.53108484817125 39.16593329791186),LINESTRING(-86.52979738784411 39.166361688165836,-86.52980811668016 39.16589170648615),LINESTRING(-86.53332181048968 39.16756990099017,-86.53276927543264 39.16756574194545),LINESTRING(-86.53233475757219 39.16844329492639,-86.53232939315416 39.167782011943274),LINESTRING(-86.53105266166308 39.16843913593334,-86.53105266166308 39.16764892279255),LINESTRING(-86.53351492953877 39.166586280071925,-86.53236157966235 39.16658004141755))
Woodlawn Reconstruction Project North Woodlawn Avenue May 7, 2018 to August 27, 2018
North Woodlawn Avenue from East 7th Street to East 9th Street may have temporary lane restrictions as construction activities are completed.
Indiana University
LINESTRING(-86.52349151445007 39.17040812819309,-86.52349687886812 39.16849085988761,-86.52457512689209 39.16849085988761)
Woodlawn Avenue Closure & 8th Street/Forrest Two-Way Traffic (05/07/2018-08/24/2018) Woodlawn Avenue May 7, 2018 to August 11, 2018
Woodlawn Avenue between 7th and 8th Streets will be closed from May 7-August 24, 2018, for underground utilities work. Traffic on 8th Street and Forrest Avenue/University Road will become two-way to serve as a detour. Schedule is subject to change.
Indiana University
GEOMETRYCOLLECTION(LINESTRING(-86.52349258772658 39.16943458405507,-86.52349258772658 39.1685162854173),LINESTRING(-86.52349258772658 39.1685162854173,-86.52348829625765 39.1685162854173))
Trades District W 10th St May 14, 2018 to October 31, 2018
W 10th St between N Morton st and N Rogers st will be closed for construction.
Planning & Transportation
LINESTRING(-86.53612471891017 39.17168307578683,-86.5366879828033 39.17168307578683,-86.53681136441797 39.17163732895733,-86.53726197553249 39.171258876771816,-86.53737616100199 39.17123808263665,-86.5380091623295 39.17125471794526,-86.53837394275553 39.171387800272555,-86.5385670618046 39.171404435545725)
Traffic Signal Work 2nd Street and Rogers Street June 11, 2018 to August 6, 2018
Traffic signal, crosswalk and sidewalk work, possible lane restrictions.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.53848303440942 39.161397214961966,-86.53889073017969 39.16139929466675),LINESTRING(-86.53868688229454 39.16156567084738,-86.53868688229454 39.16125371518589))
Traffic Signal Work 1st Street and College Avenue June 11, 2018 to August 6, 2018
Traffic signal and crosswalk work, possible lane restrictions.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.53497181895827 39.159450180112685,-86.53497450116728 39.159319154963356),LINESTRING(-86.53489269379234 39.159383627686395,-86.53507374290085 39.159383627686395))
Traffic Signal Work 2nd Street and Walker Street June 11, 2018 to August 6, 2018
Traffic signal work, possible lane restrictions.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.54600815263053 39.161440488590074,-86.5462388226058 39.16144568784861),LINESTRING(-86.54614762749931 39.16150495936904,-86.54614092197676 39.161370818488365))
Atwater Ave Sidewalk -Indiana University Atwater Ave June 27, 2018 to August 8, 2018
The northern lane of Atwater Ave between Faculty Ave and Highland Ave will be closed one block at a time west to east while Indiana University reconstructs the sidewalk on the north side of Atwater Ave. Pedestrians will be routed to the south side of Atwater Ave at Woodlawn and Jordan Ave
Planning & Transportation
LINESTRING(-86.52098577184984 39.16312156617545,-86.517767121032 39.163100769634354)
South Sage Court Water Line Installation Project South Sage Court at East Pepperridge Drive July 31, 2018 07:00 am to 15:00 pm August 24, 2018
The City of Bloomington Utilities has scheduled a water line installation project, weather permitting. Signage will be in place.
Utilities
LINESTRING(-86.52443565202314 39.12384788195561,-86.52451075387556 39.123602345428196,-86.52484334779342 39.12351078921586)
Intersection improvements with water and sewer line replacements. Walnut Street Pike, from Rhorer Road to approximately 400' south August 3, 2018 to September 7, 2018
Walnut Street Pike will be closed south of the Rhorer Road intersection. Traffic will be able to travel between Rhorer Road to the east of the intersection and Walnut St Pike to the north of the intersection. Detour will use Winslow Road, Walnut Street/Old SR 37 South and Fairfax Road.
Monroe County Highway Department
POINT(-86.52669943643191 39.12142681279482)
Winslow Farms Block Party 2000 block S. Sweetbriar Circle and a portion of S. Sweetbriar Drive after 2241 Sweetbriar Drive August 4, 2018 14:00 pm to 19:00 pm
Winslow Farm Community Association requests the Board’s permission to close a public street to hold a neighborhood block party on Saturday, August 4th (raindate, Sunday, August 5th) from 2:00 p.m. until 7:00 p.m. so their neighborhood can get together for a neighborhood block party. Pending Board approval the Petitioner will be closing down a portion of the 2000 block S. Sweetbriar Circle and a portion of S. Sweetbriar Drive after 2241 Sweetbriar Drive. A noise permit is part of the resolution so music may be played during the event.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.52541495429969 39.141772971035124,-86.5259156335341 39.14173136532668,-86.52622698204301 39.141569565129686,-86.52640579586821 39.141241340589175,-86.5263521516879 39.14097783544841,-86.52614949593206 39.14071432906738,-86.52577398666998 39.140510920230156,-86.52526734711661 39.140362986115036),LINESTRING(-86.52540443772685 39.14175447955577,-86.52494548203484 39.14174523381425,-86.52470706338298 39.14172674245455))
Prospect Hill Neighborhood Association Street Painting Party the intersection of Fairview and Howe Street August 4, 2018 10:00 am to 19:00 pm
The Prospect Hill Neighborhood Assocation will be hosting a Street Mural Painting Party on Saturday, August 4th from from 10:00 a.m. until 7:00 p.m. Prospect Hill Neighborhood is requesting permission to paint and close the intersection of Fairview and Howe Street to install a public art project in the street.
Public Works
LINESTRING(-86.54105186608044 39.16239604851239,-86.54087007193206 39.162393737754996,-86.54095351836199 39.16239604851239,-86.54095649868519 39.16248154622775)
Culvert Replacement Between Eller Road and SR 45 August 6, 2018 to August 7, 2018
This segment of roadway will be closed for a culvert replacement. The road should reopen at the end of the day on Tuesday. This project is weather permitting. Please use caution in this area.
Monroe County Highway Department
POINT(-86.64293488214112 39.1210741056297)
South Sare Road South Sare Road from East Moores Pike to East David Drive August 6, 2018
There will be single lane restrictions, both directions. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.49830223437368 39.15041707623709,-86.49896742220938 39.1496516212749,-86.49905325289784 39.14928553117605,-86.4989888798815 39.14717215565176,-86.49890304919302 39.146839334824904,-86.49855972643911 39.14637338302333,-86.49750830050526 39.14579093893363,-86.49714352007925 39.14542482875322,-86.49697185870228 39.1450753581683,-86.49688602801382 39.143960368989156,-86.49662853594837 39.14352768186444,-86.49654270525991 39.138618160900506)
Gifford Road Between Cave Road and Gifford Road August 6, 2018 to August 7, 2018
This segment of roadway will be closed for a culvert replacement.
Monroe County Highway Department
POINT(-86.63514289379196 39.15154845841468)
North Woodlawn Avenue North Woodlawn Avenue from East 7th Street to East 9th Street August 7, 2018 to August 9, 2018
Street Department will have road CLOSED. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.52347413155861 39.17042860565169,-86.52349558923073 39.16849054295693)
W. Maple Grove Road Between SR 46 and Matthews Road August 8, 2018 to August 9, 2018
This segment of roadway will be closed for a culvert replacement.
Monroe County Highway Department
POINT(-86.62924565148936 39.24570400494861)
East Rogers Road and South Sare Road Roundabout East Rogers Road and South Sare Road Roundabout. August 9, 2018 to August 10, 2018
There will be single lane restrictions, both directions for pavement markings. The work will be performed from 6:00 PM to 6:00 AM, weather permitting.
Street
GEOMETRYCOLLECTION(LINESTRING(-86.49650452866935 39.13634563254041,-86.49651257529639 39.136214564372096,-86.49654476180456 39.13610638093826,-86.49665473237417 39.13600651915951,-86.49675397410773 39.13595450776032,-86.49708120360754 39.13590457678097),LINESTRING(-86.49708120360754 39.13590457678097,-86.49681566491508 39.13581095609922,-86.49666546121023 39.135725657147475,-86.49661718144796 39.135679886935634,-86.49652598634145 39.13527835607471),LINESTRING(-86.49650721087836 39.13528251702806,-86.49645893111608 39.1354635182588,-86.49632482066535 39.13567780647077,-86.49630604520225 39.135704852509434,-86.49582056537054 39.135844243467005,-86.4958152009525 39.13589209403057,-86.49612901940726 39.135950346846755,-86.49631140962026 39.13603980643484,-86.49638114705466 39.13610638093826,-86.4964991642513 39.13633939120459),LINESTRING(-86.4974352551975 39.13582343886398,-86.49744598403356 39.13583384116623),LINESTRING(-86.49744061961553 39.135825519324555,-86.49744330182456 39.13583176070594))
Amherst Road At N. Maple Grove Road August 13, 2018 to August 14, 2018
This section of roadway will be closed for a pipe installation.
Monroe County Highway Department
POINT(-86.56103171182257 39.210257847812215)
Dillman Road Between Victor Pike and Dillman Lane August 13, 2018 to August 15, 2018
This segment of roadway will be closed for bridge maintenance. Weather permitting.
Monroe County Highway Department
POINT(-86.5539607845174 39.09300987883256)
South Fess Avenue South Fess Avenue between East Grimes Lane to E Brenda Lane August 14, 2018 to August 16, 2018
Tree Removal from 6:00 a.m. to 3:00 p.m.
Street
LINESTRING(-86.52596172417921 39.153305906747136,-86.5259693952577 39.151834081498805)
South Yancy Lane South Yancy Lane from West 3rd Street to End of City Maintenance. August 14, 2018
There will be single lane restrictions, both directions for pavement project. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.56949268452061 39.16691992373097,-86.56948732010257 39.16465318696956)
South Walnut Street Road Repair Project South Walnut Street, between East Davis Street and East/West Hillside Drive August 14, 2018 05:30 am to 08:30 am
The City of Bloomington Utilities has scheduled a road repair project, weather permitting. South Walnut Street, between East/West Hillside Drive and East Davis Street, will be reduced to two lanes with traffic traveling in either direction during the duration of the project. Additionally, southbound traffic on South Walnut will be unable to turn left onto East Grimes Lane during the hours this road repair project is underway. Signage will be in place.
Utilities
GEOMETRYCOLLECTION(LINESTRING(-86.53369274421863 39.15424275400295,-86.5337249307268 39.15336918374712),LINESTRING(-86.53369810863668 39.154215715086224,-86.53369810863668 39.15056328592729))
North Fee Lane North Fee Lane from East Law Lane to East 11th Stret August 15, 2018 to August 16, 2018
There will be single lane restrictions, both directions for pavement project. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.51887811494365 39.17399595521127,-86.51889957261577 39.17330561350812)
South Sare Road South Sare Road from East Rogers Road to East Canada Drive August 15, 2018 to August 30, 2018
There will be single lane restrictions, both directions for pavement milling/resurface project. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.49648703408798 39.135492821398,-86.49652994943223 39.13502679449127,-86.49764574838242 39.13387835787714,-86.49901903939805 39.13274654694692,-86.50039233041367 39.131881032196674,-86.50118626428208 39.131381691924986,-86.5018729097899 39.130699254494345,-86.50240935159287 39.13010003568817,-86.50337494683824 39.128219121317244,-86.50427616906724 39.12657119930259)
Union Board Block Party and Concert E. 13th Street between N. Fee Lane and N. Walnut Grove August 17, 2018 08:00 am to 01:30 am August 19, 2018
The IU Union Board is requesting the closure of E. 13th Street between N. Fee Lane and N. Walnut Grove from 8:00 a.m. Friday, August 17 thru Sunday, August 19th at 1:30 a.m. for a concert and block party to welcome students back to school.
Public Works
LINESTRING(-86.5210536863705 39.17513976344247,-86.519086733966 39.175102798521834)
Second Baptist Church Picnic West 8th Street August 18, 2018 to August 19, 2018
West 8th Street will be closed between North Jackson Street to North Rogers Street on 8-18-2018 from 7:00 a.m. to 6:00 p.m. for the Second Baptist Church Picnic.
Public Works
LINESTRING(-86.53869244789682 39.169537884134684,-86.53981897568308 39.1695628376994)
East 15th Street East 15th Street from North Lincoln Street to North Dunn Street August 20, 2018 to September 28, 2018
There will be single lane restrictions, both directions for sidewalk and ADA ramp installation/repairs. The work will be performed from 7:00 am to 3:00 pm, weather permitting.
Street
LINESTRING(-86.53097487760122 39.176854563117104,-86.52843750787315 39.176879514085556,-86.52835167718466 39.17694604995805)
Ketcham Road 7698 Block, approximately 4,850' south of Fluckmill Road August 20, 2018 to August 22, 2018
This segment of roadway will be closed for a pipe replacement. Weather permitting.
Monroe County Highway Department
POINT(-86.57897032571407 39.06461617297796)
IU UNION BOARD STUDENT INVOLVEMENT FAIR close 7th Street between Woodlawn and Indiana August 20, 2018 08:00 am to 21:00 pm
IU Union Board would like to close 7th Street between Woodlawn and Indiana on August 20, 2018 from 8:00 a.m. until 9:00 p.m. for the Student Involvement Fair as they have done in the past. The Student Involvement Fairs is an annual event that provides students the opportunity to meet with and learn about ways to get involved on campus. This year, the event will be on the first day of classes from 3 – 7 p.m. (shifting the time to accommodate class schedules and move it out of the hottest time of the day).
Public Works
LINESTRING(-86.52692474329878 39.16848384560333,-86.5234795951218 39.16849308757824)
Friendship Road Approximately 2,500' south of SR 46 at the bridge. August 21, 2018 to August 23, 2018
This segment of roadway will be closed to conduct bridge maintenance. Weather permitting.
Monroe County Highway Department
POINT(-86.40739477944938 39.14769101864309)
North Madison North Madison between West 6th Street and West 7th Street. August 21, 2018 to August 22, 2018
North Madison between West 6th Street and West 7th Street will have lane restrictions between 7:00 a.m. to 3:00 p.m. for tree and stump removal.
Street
LINESTRING(-86.53739697320452 39.168565815414865,-86.53738033005169 39.16758646104313)
West 7th Street West 7th Street between North Madison Street and North Rogers Street August 22, 2018 to August 23, 2018
West 7th Street between North Madison Street and North Rogers Street will have lane restrictions between 7:00 a.m. to 3:00 p.m. for tree and stump removal.
Street
LINESTRING(-86.53739621860605 39.168566787721204,-86.53861597992184 39.16859749142455)
S Henderson St Between 1st St and University St August 23, 2018
The northbound and southbound lanes of Henderson St between 1st and University will be restricted to one lane between 9am-3pm while a sewer lateral is placed. Flaggers will be in place to direct traffic.
Planning & Transportation
LINESTRING(-86.52719296289062 39.160370226387386,-86.52713931871033 39.159355308318624)
Friendship Road Approximately 2,400' south of SR 46 at the bridge August 24, 2018 to August 30, 2018
This segment will remain closed for bridge maintenance.
Monroe County Highway Department
POINT(-86.40739477944942 39.14770765952045)
Bryan Park Neighborhood Block Party South Palmer Avenue between East Driscoll Drive and East Grimes Lane August 24, 2018 17:00 pm to 22:00 pm
Bryan Park Neighborhood Association requests the Board’s permission to close a public street to hold their annual neighborhood block party on Friday, August 24, 2018 from 5:00 p.m. to 10:00 p.m. to allow for set up and tear down, with a rain date of Saturday, August 25, 2018. The actual party will run from 6:00 p.m. until 9:00 p.m.
Public Works
LINESTRING(-86.5292119256431 39.152452345472,-86.5292119256431 39.1533582820025)
Pridefest Kirkwood, Dunn, Grant August 25, 2018 21:00 pm to 01:00 am August 26, 2018
The Bloomington PRIDE Pridefest is requesting the use Kirkwood Avenue east side of Washington Street intersection through west side of Dunn St. intersection, as well as North Grant Street one half block to the north, and South Grant, one block to the south on Saturday, August 25, 2018 from 9:00 P.M. on Friday the 24th until 1:00 A.M. Sunday the 26th for its annual event. PRIDE agrees not to close E. Kirkwood Avenue from North Washington to North Lincoln until 1:00 p.m. on August 25th so that patrons will still have access to People’s State Bank.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53226412825089 39.16659194095985,-86.5282944595637 39.16653648607013),LINESTRING(-86.52976073338861 39.167063303980285,-86.52980841724995 39.16609284690139))
Japanese Summer Event Festival South Susie Street closed August 25, 2018 to August 26, 2018
Susie Street requests the Board’s permission to close a public street to hold their annual neighborhood Japanese Summer Event Festival to be held between 3:00 pm to 9:00 pm on 8-25-18. South Susie Street will be temporarily closed to motor vehicles during these times.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.54215321453387 39.144338082611625,-86.54213175686175 39.144354724281726),LINESTRING(-86.54212102802568 39.14434744355157,-86.54210895808511 39.144405689371894,-86.5420888415175 39.14442753154208,-86.54205263169581 39.14444001277914,-86.54200703414256 39.14444521329392,-86.54186353596025 39.144442092985116,-86.54182464392953 39.14443273205782,-86.5417830696898 39.14440360916487,-86.54177904637626 39.14431728051858,-86.54181391509347 39.144266315364405,-86.54204860838227 39.14426111483641,-86.54210895808511 39.14429335810385,-86.54211566360765 39.1443464034472))
Vernal Pike East of Curry Pike August 27, 2018 to August 29, 2018
This segment of road will be having crack sealing operations conducted during the day. This will be under flagging operations, weather permitting.
Monroe County Highway Department
LINESTRING(-86.58302582574456 39.179168519737885,-86.57564438653557 39.17906871906035,-86.57379902673333 39.179301587087565,-86.56736172509758 39.17923505344419,-86.56397141290276 39.179201786598924,-86.56315602136223 39.17913525286113)
South Fess Avenue South Fess Avenue from East 1st Street to East University Street August 27, 2018 to August 28, 2018
Street will be closed both directions for a tree removal project. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.52591267985024 39.160386559342214,-86.52593413752236 39.15933004620362)
Isaac Dive between Westplex and patterson dr August 27, 2018
Isaac Drive between Patterson and Westplex will have a one-lane closure Monday, 8/27 between 8am and 5 pm. Signage will be in place.
Planning & Transportation
LINESTRING(-86.55378986223934 39.163439759504655,-86.55318368300196 39.16341896305761,-86.55273307188747 39.163327458617715,-86.55180648588708 39.163309876504144,-86.55129150175622 39.16340969954854)
East Pepperridge Drive Water Project East Pepperridge Drive, between East Heather Drive and East Heather Drive August 27, 2018 07:30 am to 15:30 pm October 12, 2018
The City of Bloomington Utilities has scheduled a water line project, weather permitting. Signage will be in place.
Utilities
LINESTRING(-86.52501917779351 39.12419560255995,-86.52441836297417 39.12383770334023,-86.52379609048272 39.12387515799492,-86.52271784245873 39.124595115820114,-86.52254081666374 39.1248364873168,-86.52250863015557 39.1253774893911,-86.52266419827843 39.1256854425622,-86.52295924127006 39.12598090987973)
1000 Block South Ballantine Road 1000 Block South Ballantine Road from South Southdowns Drive to Dead End August 28, 2018
There will be single lane restrictions, both directions for pavement repair project. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.51927588183021 39.15577680224695,-86.51928124624826 39.155323388924415,-86.51924905974006 39.15498644685661,-86.51908276278114 39.15445815172447)
Fountain Dr Between 11th and Adams August 28, 2018 to August 29, 2018
Fountain Drive between Adams and 11th will have a one-lane closure (northbound and southbound) Tuesday, 8/28 and Wednesday 8/29 between 8 am and 3:30 pm for a utility connection. Flaggers and signage will be in place to direct traffic.
Planning & Transportation
LINESTRING(-86.55473388505554 39.17278930823926,-86.5543476469574 39.172423338527125,-86.55384339166261 39.17210727224301)
1000 Block South Jordan Avenue 1000 Block South Jordan Avenue from South Sheridan Drive to South Southdowns Drive August 28, 2018
There will be single lane restrictions, both directions for pavement repair project. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.51560882438851 39.156102886145106,-86.515340603487 39.155728510117655,-86.51515821327399 39.15527093671227)
East 2nd Street East 2nd Street Closed between South Woodlawn Avenue to South Hawthorne Drive August 29, 2018 to August 30, 2018
Road closed for tree removal.
Street
LINESTRING(-86.52019548257971 39.16107907185929,-86.52262223787051 39.16108697474735)
South Dunn Street South Dunn Street from East 3rd Street to East Kirkwood Avenue August 29, 2018 to August 30, 2018
There will be single lane restrictions, both directions for pavement milling/resurface project. The work will be performed from 6:00 am to 4:00 pm, weather permitting.
Street
LINESTRING(-86.52821341046904 39.1665321071913,-86.5282455969772 39.164444205023045)
South Olive St - Lane Restriction South Olive St off of East Miller Drive August 30, 2018 to August 31, 2018
Tree Removal
Street
LINESTRING(-86.51877122275258 39.14682999748052,-86.51878399009365 39.146824048291876,-86.51878144179865 39.14637829468168)
East 7th Street Sanitary Sewer Repair Project East 7th Street, between North Washington Street and North Walnut Street August 30, 2018 07:00 am to 16:00 pm
The City of Bloomington Utilities has scheduled a sanitary sewer repair project, weather permitting. Two-way traffic on East 7th Street during the duration of the project. Signage will be in place.
Utilities
LINESTRING(-86.53357806222118 39.16855303823695,-86.53236033932843 39.16854472026361)
E 3rd St E 3rd street between Walnut and Washington August 30, 2018 to August 31, 2018
There will be a one lane closure eastbound and westbound on E 3rd St between Walnut and Washington between the hours of 7:30p-6:30a on 8/30/2018
Planning & Transportation
LINESTRING(-86.53240181279752 39.16460443969973,-86.53357125592801 39.16461275813907)
Tree Removal South Walnut between West 3rd and West 4th August 30, 2018
South Walnut between West 3rd and West 4th will have right turn lane restriction for tree removal.
Street
LINESTRING(-86.53364015784992 39.164615492269746,-86.53362991162814 39.16558990743707)
Walnut Street Pike Walnut Street Pike at Rhorer Road, extending south for approximately 400 feet. August 30, 2018 to September 28, 2018
This segment of roadway will close for the reconstruction of the roadway and water line installation. This is scheduled for a 30 day closure, weather permitting.
Monroe County Highway Department
GEOMETRYCOLLECTION(POINT(-86.52665304301135 39.12131085813098),LINESTRING(-86.52666377184741 39.12131085813098,-86.52665304301135 39.121452358464154))
The 42nd Annual 4th Street Festival of the Arts and Crafts Fourth, Grant and Dunn Streets August 31, 2018 14:00 pm to 22:00 pm September 2, 2018
Planners for the 4th Street Festival of the Arts and Crafts wish to request the closure of Fourth, Grant and Dunn Streets Friday, September 1st through Sunday, September 3rd for this year’s 42nd annual festival which will be September 2nd and 3rd, 2017. This year’s festival will again utilize the same street layout as it did in 2017. The Street Closure time has been amended from the application to a 2:00 p.m. Friday, August 31st closure time to allow for a longer set up time for artists.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53108619631982 39.16557135526904,-86.52687810767107 39.165534384811),LINESTRING(-86.52979873599266 39.16658803220466,-86.52988218176776 39.16461936257414),LINESTRING(-86.52829669894433 39.16652333507932,-86.5282609357209 39.16447147913149))
East 7th Street Road Repair Project East 7th Street, between North Walnut Street and North Washington Street. August 31, 2018 08:30 am to 14:00 pm
The City of Bloomington Utilities is doing a road repair project. Two-way traffic will be maintained for the duration of the work. Signage is in place.
Utilities
LINESTRING(-86.53359807801816 39.16856702485694,-86.53233743978116 39.168550388912564)
W Tapp Rd W Tapp Rd between S Kegg Rd and Adams St September 1, 2018 to October 27, 2018
There will be lane shifts on W Tapp Rd between S Kegg and S Adams beginning 9/1 and ending 10/27. Signage and barricades will be in place to direct vehicular traffic. Expect lanes to shift and signage to change as listed: • Phase 1 9/1/18-9/22/18 • Phase 2 9/22/18-10/13/18 • Phase 3 10/14/18-10/27/18
Planning & Transportation
LINESTRING(-86.56017958145783 39.13653360166177,-86.55524431687041 39.13650863638185)
Earl Young Bridge Maintenance Earl Young Road, the 5035 block, between Lentz Road and Everett Arnold Drive September 4, 2018 to September 6, 2018
This segment of roadway will be closed for bridge maintenance activities. There can be some intermittent full closure during the day time hours. Please use caution while traveling in the area.
Monroe County Highway Department
POINT(-86.45765609096647 39.229675493644976)
W 3rd St Between Landmark Ave and Cory Lane September 4, 2018
One lane westbound closure on W 3rd St between Landmark Ave and Cory Ln between the hours of 9a-3:30p
Planning & Transportation
LINESTRING(-86.56006237141312 39.164496299898644,-86.55919870011033 39.164492140672195)
East 2nd Street Water Infrastructure Project East 2nd Street, between South Rose Avenue and South Clifton Avenue. September 4, 2018 09:00 am to 10:30 am
The City of Bloomington Utilities has scheduled a water infrastructure improvement project, weather permitting. Two-way traffic will be maintained for the duration of the project. Signage and traffic control personnel will be in place.
Utilities
LINESTRING(-86.5115610487518 39.16102637976388,-86.5097049601135 39.161001423170546)
North Madison Street North Madison Street from West 11th Street to West 17th Street September 4, 2018 to September 14, 2018
There will be single lane restrictions, both directions for pavement milling/resurface project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.53772867990095 39.17902775925961,-86.53770722222885 39.175975451671235,-86.53770722222885 39.17559286426305,-86.53846896958908 39.17419557082633,-86.53856552911361 39.173330565736165)
E 3rd St between Walnut and Washington September 4, 2018 to September 11, 2018
One lane closure westbound on E 3rd St between Walnut and Washington beginning 9/4/2018 and ending 9/11/2018.
Planning & Transportation
LINESTRING(-86.53240279614671 39.16460010107926,-86.53357760369522 39.164612578738684)
West Runkle Way West Runkle Way off of North Gates Drive September 4, 2018 to September 6, 2018
West Runkle Way off of North Gates Drive will have lane restriction for tree removals.
Street
LINESTRING(-86.57781821929399 39.16636673174108,-86.57850027816544 39.16636475613572)
CFC Properties Fountain Square Mall 30th Anniversary Celebration Event West Kirkwood Street Between North College Avenue and North Walnut Street. September 4, 2018 to September 5, 2018
CFC Properties requests the Board’s permission to close a public street to hold Fountain Square Mall 30th Anniversary Celebration Event between the hours of 6 a.m. and 9 p.m. on Tuesday September 4, 2018: West Kirkwood Street Between North College Avenue and North Walnut Street.
Public Works
LINESTRING(-86.53486303839809 39.166602819208265,-86.53362922225124 39.166590341901895)
Turn lane and bike lane restriction for building facade renovation. 701 N. College Ave. September 5, 2018 to September 18, 2018
Contractors are working on the exterior of the Station 11 Building. The westernmost turn lane is restricted. The bike lane has been restricted to accommodate a pedestrian walk-around.
Planning & Transportation
LINESTRING(-86.5348279933059 39.17385837889475,-86.53483286987097 39.17331018810938)
East 4th Street Closed East 4th Street Closed between South Washington Street and South Lincoln Street September 8, 2018 to September 10, 2018
East 4th Street between S Washington and S Lincoln will be closed from 4:oo pm 9-8-18 to 4:00 pm 9-9-2018 for the First United Methodist Church Annual Picnic
Public Works
LINESTRING(-86.53233168681645 39.16558678425412,-86.53109250625157 39.16558262509213)
Blue Ridge Neighborhood Block Party E Oliver Drive September 9, 2018 15:30 pm to 20:00 pm
Blue Ridge Neighborhood Association requests the Board’s permission to close a public street to hold their annual neighborhood block party on Sunday, September 9th, 2018 from 3:30 p.m. to 8:00 p.m. to allow for set up and tear down, with a rain date of Sunday, September 16, 2018.
Public Works
LINESTRING(-86.53387446493048 39.20298960923549,-86.53337557405372 39.20296051058452,-86.53303225129979 39.20299376618462,-86.53158922284977 39.203151730069976)
North Kinser Pike North Kinser Pike from Cougar Drive to ECM September 10, 2018 to September 18, 2018
There will be single lane restrictions, both directions for pavement milling/resurface project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.54725696492885 39.20108959984347,-86.54738571096156 39.20770733034209)
North Jefferson Street North Jefferson Street from East 7th Street to East 8th Street September 10, 2018 to September 11, 2018
There will be single lane restrictions, both directions for tree removal project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.50715784454773 39.169499698286046,-86.50714711571167 39.168243690074945)
Northbound lane of S. Henderson restricted S. Henderson and E. Hillside September 10, 2018 10:30 am to 12:30 pm
The northbound lane of S. Henderson will be restricted for 2 hours to facilitate a delivery. Flaggers and signage will be in place.
Planning & Transportation
LINESTRING(-86.52688914051028 39.15049642065566,-86.52689889396784 39.15003124946659)
2513 S Rogers Between Coolidge and Country Club September 11, 2018
northbound lane closure for one hour
Planning & Transportation
LINESTRING(-86.53858762143807 39.139469309341564,-86.5383408582087 39.137347317425366)
WFHB 25th Anniversary Street Party W 4th Street Between South College & South Walnut (parking garage access will remain open) September 15, 2018 14:00 pm to 00:01 am September 16, 2018
W 4th Street Between South College & South Walnut (parking garage access will remain open) Closure of east west alley from S College to parking garage, and north south alley from 4th Street to east west alley, and parking from 2:00 pm on Saturday, September 15,2018 until 12:00 a.m. on Sunday September 16, 2018.
Public Works
LINESTRING(-86.53488151503147 39.1656053489539,-86.53363562894405 39.16559807042222)
West 8th Street West 8th Street from North Morton Street to North College Avenue September 17, 2018 to September 21, 2018
There will be single lane restrictions, both directions for crack sealing project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.53610862565577 39.169512771925724,-86.53477824998438 39.16949613620503)
Eastern Heights Eastern Heights Neighborhood Project September 17, 2018 to October 1, 2018
There will be single lane restrictions, both directions for pavement resurface project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
GEOMETRYCOLLECTION(LINESTRING(-86.47925575316815 39.176180407356895,-86.47867639602093 39.17553167284967,-86.47821505607037 39.17578950394744,-86.47808631003767 39.176313480362126,-86.47682030738262 39.176288529192846,-86.47678812087443 39.175415232689176,-86.47675593436627 39.174899566803305,-86.47710469926777 39.17447578336768,-86.47866566718487 39.1725790235177),LINESTRING(-86.47880514205364 39.175440184168394,-86.4767988497105 39.17539859836478),LINESTRING(-86.47866566718487 39.17553167284967,-86.4798780256596 39.17481639453209,-86.48025353492169 39.17450865627302,-86.4808650785771 39.17385990634159,-86.4813371473637 39.17356879865767,-86.48172338546185 39.17350225958927,-86.48208816588787 39.173593750792094),LINESTRING(-86.48082216323284 39.17383495430161,-86.48065050185589 39.173152928447166,-86.48045738280683 39.17300321456929,-86.47992094100384 39.17300321456929,-86.47954543174176 39.173186198154525,-86.47842963279156 39.174442118093964),LINESTRING(-86.4802213484135 39.17449202173418,-86.47712071479228 39.174483704463285))
East Daniel Street East Daniel Street from South Forrester Street to South Forrester Street September 17, 2018 to September 21, 2018
There will be single lane restrictions, both directions for crack sealing project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.49470258657578 39.137610449291344,-86.49335075323229 39.13756051948627)
East 8th Street East 8th Street from North Walnut Street to North Washington Street September 17, 2018 to September 21, 2018
There will be single lane restrictions, both directions for crack sealing project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.53359066371806 39.16952222243913,-86.53231393222698 39.16949726885997)
East Blue Ridge Drive East Blue Ridge Drive from North Walnut Street to North Blue Ridge Drive September 17, 2018 to September 21, 2018
There will be single lane restrictions, both directions for crack sealing project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.53450476866355 39.196849647046065,-86.53397369127862 39.19709492806149,-86.53354453783625 39.19742751112142)
Rockport Road Between Bolin Lane and Stansifer Lane September 17, 2018 to September 20, 2018
This segment of roadway will be closed for a culvert replacement. This project is weather permitting and the detour route will be posted. Please use caution in this area.
Monroe County Highway Department
POINT(-86.57495774102793 39.10411171469647)
Rockport Road Between Bolin Lane and Shaw Road, approximately 100' north of Bolin Lane September 17, 2018 to September 20, 2018
This segment of road will be closed for a culvert replacement. Detour route will be posted. This project is dependent on the weather. Please use caution in this area.
Monroe County Highway Department
POINT(-86.57502211404416 39.104211621694645)
N. Maple Grove Road N. Maple Grove and Delap Road Intersection September 18, 2018
This intersection will be closed from approximately 9:00 am to 2:00 pm for a culvert installation.
Monroe County Highway Department
POINT(-86.56935728860475 39.26527690162732)
South Walnut Street (Northbound Lane) South Walnut Street from East Grimes Lane to East Hillside Drive September 18, 2018
There will be single lane restrictions, northbound lane for pavement milling/resurface project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.53371609521466 39.15336595382132,-86.53371609521466 39.150487254955806)
S Walnut St S Walnut between Hillside and Southern Dr September 21, 2018 to September 23, 2018
Walnut St southbound lane closure between Hillside and Southern Dr. Friday 9a-3:30p, Saturday and Sunday closed during day, open at night.
Planning & Transportation
LINESTRING(-86.53372481231759 39.150723765354286,-86.53369262580941 39.150490802697135,-86.5334941423423 39.14980855047929)
BLOOMINGFOODS CO-OP VENDORS FAIR 10:00AM-1:00PM MADISON STREET BETWEEN 6TH & 7TH September 22, 2018 06:00 am to 15:00 pm
The Vendor Fair is to show appreciation for the members of their co-op community. There will be local vendors, grilling, beer sampling and live music. The event will take place alongside the Saturday Farmer’s Market. This is a family friendly event, and the general public is welcome and encouraged to attend. There is no rain date this year.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53739754758142 39.16856628537025,-86.53738145432735 39.16759515551698),LINESTRING(-86.53738145432735 39.16759515551698,-86.5373921831634 39.16759307599543))
South Pete Ellis Drive South Pete Ellis Drive - South of East Longview Avenue September 24, 2018
Tree and Stump removal
Street
LINESTRING(-86.49493224507789 39.16690791374418,-86.49491883403282 39.165635222613616)
South Baytree Lane Water Services Project South Baytree Lane, between East Pepperridge Drive and East Pepperridge Drive September 24, 2018 to September 28, 2018
The City of Bloomington Utilities has scheduled a water services project, weather permitting. Signage will be in place.
Utilities
LINESTRING(-86.52269758058156 39.124596971157445,-86.52248300386039 39.12423907397701,-86.52251519036855 39.123772972597294,-86.52247227502431 39.12365644677047,-86.52260102105704 39.12361483035707,-86.5227404959258 39.12361483035707,-86.52325548005668 39.12361483035707,-86.5235129721221 39.123648123489744,-86.52373827767934 39.123831235438416)
Arlington Rd Arlington Rd north of 17th St to Prow Road September 24, 2018 to January 1, 2019
E&B Paving, working on behalf of the City of Bloomington Utilities, has scheduled a water line installation project, weather permitting. To facilitate this work, it will be necessary to reduce traffic at this location to one lane of two-way traffic during the hours work is underway, . Signage and traffic control personnel will be in place.
Planning & Transportation
GEOMETRYCOLLECTION(LINESTRING(-86.54727734399412 39.179301587087565,-86.54809273553467 39.179700787625336,-86.54873646569823 39.180332850507654,-86.5498093493042 39.18199614672781,-86.55010975671387 39.182727984597165,-86.5501526720581 39.18402531482246,-86.55023850274658 39.184723867333986,-86.551397217041 39.18698579925939,-86.5518263704834 39.18831631344736),LINESTRING(-86.55178345513914 39.18834957597937,-86.55178345513914 39.18834957597937))
East University Street East University Street between Ballantine Road and South Hawthorne Drive September 25, 2018
For tree and stump removal
Street
LINESTRING(-86.51912353706918 39.16018740252349,-86.52021787834725 39.16018012343119)
South Weimer Road South Weimer Road from West Bloomfield Road to West Tapp Road September 27, 2018 to September 28, 2018
There will be single lane restrictions, both directions for pavement resurface project. The work will be performed from 7:00am to 3:00pm, weather permitting.
Street
LINESTRING(-86.56425036264054 39.15418128643435,-86.5639928705751 39.144130404543205,-86.56356371713272 39.143531300032606,-86.56279124093643 39.143298313568124,-86.56201876474013 39.142632633706256,-86.56214751077286 39.13670780561583)
Lotus World Music and Arts Festival 2018 West 6th St & West 4th St Between College & Walnut St September 27, 2018 to September 30, 2018
West 6th Street from North College and North Walnut and West 4th Street between South College and South Walnut will be closed from 7:00 a.m. Thursday, September 27 until Sunday, September 30th at 4:00 pm. (NOTE: 4th St Parking Garage remains OPEN and accessible throughout the weekend!!)
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.53486642494033 39.16757539247098,-86.53360578670335 39.16756499485962),LINESTRING(-86.53361115112138 39.167573312948804,-86.53361115112138 39.16756707438199),LINESTRING(-86.53489056482131 39.16560605745187,-86.53363529100231 39.16559773912999))
Lotus World Music and Arts Festival 2018 Kirkwood between Walnut St & Washington St September 28, 2018 07:00 am to 09:00 am September 30, 2018
E Kirkwood from N Walnut St to N Washington St from 7:00 am Friday, September 28, 2018 until 9:00 am Sunday, September 30, 2018 and all connecting alleys will be closed.
Public Works
LINESTRING(-86.53360954957935 39.16658747464413,-86.53233550029728 39.16658227576562)
Lotus World Music and Arts Festival 2018 North Washington Street from E 7th to E 4th E 6th St from N Washington to North Lincoln September 28, 2018 to September 30, 2018
Washington St closed from 4th to 7th st and all connecting alleys (NOTE: Washington St between 6th & 7th will be ONLY accessible to residents of the block) ** 6th St from Washington St to Lincoln St and all connecting alleys will be closed
Street
GEOMETRYCOLLECTION(LINESTRING(-86.53234075164487 39.168549998481524,-86.53232465839076 39.16854583949478,-86.5323300228088 39.16756015270275,-86.53234075164487 39.16558873767619),LINESTRING(-86.53234075164487 39.16558873767619,-86.53234075164487 39.16559289683778),LINESTRING(-86.53234075164487 39.16558873767619,-86.53234075164487 39.16558873767619),LINESTRING(-86.5323300228088 39.16756015270275,-86.5310693845718 39.1675435165202),LINESTRING(-86.53105865573573 39.1675435165202,-86.5310693845718 39.1675435165202),LINESTRING(-86.53109084224391 39.16756015270275,-86.53107474898982 39.16753935747397))
E Kirkwood Ave E Kirkwood Ave Between S Washington St & S Lincoln St September 28, 2018 09:00 am to 12:30 pm September 30, 2018
E Kirkwood Ave Between S Washington St and S Lincoln St including all connecting alleys will be closed on Friday September 28th from 9:00 a.m. to 12:30 a.m. and again 4:00 pm to 12:30 a.m on Saturday September 29th.
Public Works
LINESTRING(-86.53232939315401 39.166580665384544,-86.53109021258913 39.1665640289703)
Lotus World Music and Arts Festival 2018 E 6th St September 28, 2018 07:00 am to 15:00 pm September 30, 2018
E 6th St will be closed between North Walnut St & North Washington St, and alley running North to midpoint of block.
Public Works
LINESTRING(-86.53361417127263 39.167568445425985,-86.53232671094547 39.16756220685872)
Hoosiers Outrun Cancer E 17th, N Indiana, E 13th, E Cottage Grove, E 11th, N Walnut Grove, N Fee, E Law, N Jordan, N Dunn, and N Woodlawn September 29, 2018 09:00 am to 11:30 am
The City of Bloomington Board of Public Works agrees that all or a portion of the following City streets may be utilized to conduct the Bloomington Hospital Foundation Hoosiers Outrun Cancer between the hours of 9:00 am and 11:30 am, on Saturday, September 29, 2018: E. 17th Street, N. Indiana Avenue, E. 13th Street, E. Cottage Grove, E. 11th Street, N. Walnut Grove, N. Fee Lane, E. Law, N. Jordan, N. Dunn Street and N. Woodlawn Avenue.
Public Works
LINESTRING(-86.52682634135583 39.183141096933014,-86.52685018263168 39.183954236350075,-86.51912542066877 39.18378791313211,-86.51559682540704 39.18375095225076,-86.51419015608137 39.183473746036356,-86.51252122486352 39.18242035163959,-86.51147218515274 39.18155175142962,-86.51094766398768 39.1803319968362,-86.51089997881667 39.17885347881531,-86.51252122486352 39.17885347881531,-86.51252122486352 39.177393410296645,-86.51283116930738 39.17656171265645,-86.51385637036168 39.17539731943194,-86.51521535713567 39.17386324801521,-86.51550145768435 39.17338268923842,-86.51895852911859 39.17399262971759,-86.5190777381171 39.17523097596862,-86.52100892860784 39.17512008078464,-86.52108045243533 39.17255094415657,-86.52696939293986 39.17253246025672,-86.52704091807702 39.179038294887675,-86.52665944849598 39.17907525824688,-86.52687402521717 39.17972211236449,-86.5271124432142 39.18049832873879,-86.52730317865957 39.18094187703218,-86.52694555035434 39.179999332865634,-86.52663560591049 39.179056777077335,-86.5282330106815 39.17901981370838,-86.52832837840418 39.18406511810758,-86.52794690882313 39.184157519861515,-86.52792306754729 39.18474888643388,-86.5280184339603 39.18515544801872,-86.52816148554433 39.185543527280174,-86.52768464824061 39.185802245682,-86.52687402521717 39.18574680619531,-86.52687402521717 39.18382487399401)
Tamarron HOA Block Party North Callery Drive between addresses 808 and 806 September 29, 2018 16:00 pm to 22:00 pm
Tamarron HOA requests the Board’s permission to close a public street to hold a neighborhood block party on Saturday, September 29, 2018 from 4:00 p.m. until 10:00 p.m. so their neighborhood can get together for a neighborhood block party. Pending Board approval the Petitioner will be closing down a portion of the North Callery Drive between addresses 808 and 806.
Public Works
LINESTRING(-86.48496896393164 39.17525712425589,-86.48546964251118 39.174785816153076)
East Elliston Drive East Elliston Drive from South Bainbridge Drive to Dead End October 1, 2018 to October 5, 2018
There will be single lane restrictions, both directions for sidewalk installation/repairs. The work will be performed from 7:00 am to 3:00 pm, weather permitting.
Street
LINESTRING(-86.51929416889323 39.12906014280247,-86.51870408290996 39.12920162756947,-86.5179745220579 39.12920995019394,-86.51758828395977 39.12930982161123,-86.51660123104229 39.12999227250566,-86.51636519664898 39.13005053020251,-86.51618280643596 39.13005053020251,-86.51592531437053 39.130017240095924,-86.51457348102703 39.12942633808575,-86.51438036197794 39.129418015486806,-86.51398339504377 39.129509564020935)
East Hector Dr 4100 Block of East Hector Drive October 1, 2018 to October 2, 2018
Lane restriction due to paving.
Street
LINESTRING(-86.48056753912645 39.17307202234281,-86.48058925152985 39.17305419183839)
South Baytree Lane Street Repair South Baytree Lane, between East Pepperridge Drive and East Pepperridge Drive October 1, 2018 07:30 am to 15:30 pm October 12, 2018
The City of Bloomington Utilities has scheduled a street repair project, weather permitting. Signage will be in place.
Utilities
GEOMETRYCOLLECTION(LINESTRING(-86.52378119302354 39.12384788195564,-86.52353979421218 39.12367725496799,-86.52317501378614 39.12361483035707,-86.52274586034379 39.1236314769254,-86.52252055478652 39.123739679523624,-86.52248300386033 39.12393527610635,-86.52250446153245 39.12417248825449,-86.52254737687669 39.12435976043878,-86.52263320756514 39.12450957782775,-86.52269221616349 39.12457616323164),LINESTRING(-86.52271367383563 39.124592809572846,-86.52269221616349 39.12458032481729),LINESTRING(-86.52268685174545 39.12458448640274,-86.5226761229094 39.12457200164579))
South Weimer Road South Weimer Road Between Wesst Wapehani Road and West Tapp Road October 2, 2018 to October 4, 2018
Lane restriction due to paving.
Street
LINESTRING(-86.5638838639241 39.14401607793894,-86.56235114256181 39.143049351702615,-86.56216725015453 39.142668915330574,-86.56196275922025 39.13658248167545)
IU Fine Arts E. 13th Street from Fess Avenue to Woodlawn Avenue. October 3, 2018 to October 26, 2018
Weddle Brothers has been contracted by IU to perform a renovation on the building located at 802 E. 13th Street.
Public Works
GEOMETRYCOLLECTION(LINESTRING(-86.52475291516149 39.17521819290104,-86.52362638737522 39.17518492415513),LINESTRING(-86.52362638737522 39.175201558530034,-86.52362638737522 39.17518492415513),LINESTRING(-86.52362638737522 39.17519324134307,-86.52362638737522 39.175201558530034),LINESTRING(-86.52362638737522 39.175201558530034,-86.52371221806371 39.17519324134307))
East Pierson Court East Pierson Court off of South The Stands Drive October 4, 2018 to October 6, 2018
Closed for paving.
Street
LINESTRING(-86.51005533832164 39.12826386981493,-86.51005533832164 39.12826386981493,-86.51049725910514 39.12825197871274)
Arlington Rd Arlington Rd between 17th and 20th St October 8, 2018 to October 9, 2018
A lane closure on the north side of the roundabout will result in flaggers at each leg of the roundabout. This lane closure will be in place all day while MCCSC students are on Fall Break 10/8-10/9. More information below: E&B Paving, working on behalf of the City of Bloomington Utilities, has scheduled a water line installation project, weather permitting. To facilitate this work, it will be necessary to reduce traffic at this location to one lane of two-way traffic during the hours work is underway, . Signage and traffic control personnel will be in place
Planning & Transportation
LINESTRING(-86.54760993791197 39.17939307074437,-86.5480820066986 39.17966752100048,-86.5485326178131 39.18003761131598,-86.54880620313261 39.18036195852983)
Intersection of E 10th Street and North Forrest Avenue E 10th Street and North Forrest Avenue October 8, 2018
There will be single lane restrictions, both directions for street resurface. The work will be performed from 7:00 am to 3:00 pm, weather permitting.
Street
GEOMETRYCOLLECTION(LINESTRING(-86.5223894972904 39.17176667860352,-86.52238413287238 39.17162943818889),LINESTRING(-86.52251287890509 39.171633596993274,-86.52227684451177 39.17162943818889))
North Fee Lane North Fee Lane from East 11th Street to East Lawn Lane October 8, 2018 to October 10, 2018
There will be single lane restrictions, both directions for pavement markings. The work will be performed from 7:00 am to 3:00 pm, weather permitting.
Street
LINESTRING(-86.51888406060034 39.1739774665152,-86.51888406060034 39.17326217238735)
East Thornton Drive East Thornton Drive between South Olive Street & South Huntington Drive October 9, 2018 to October 11, 2018
East Thornton Drive will be closed between 7 a.m. and 3:00 for tree and stump removal.
Street
LINESTRING(-86.51881407490642 39.149468377976234,-86.52081425173441 39.149299997135756)
East 1st Street 1200 block of East 1st Street between South Highland Avenue and South Ballantine Road October 10, 2018 to October 11, 2018
Road will be closed between 7:00 a.m. and 3:00 p.m. for tree and stump removal, weather permitting.
Street
LINESTRING(-86.51772845511547 39.159266578102574,-86.51910276571104 39.15927448119422)
iU Homecoming Parade Woodlawn Ave between 17th Street and 7th Street Closure of Woodlawn Ave both North and South lanes from 7th Street to 17th Street. October 12, 2018 17:00 pm to 21:00 pm
City of Bloomington will be closing both the North and South bound lanes of Woodlawn Ave from 7th Street to 17th Street on 10/12/2018 between 5pm-9pm for the IU Homecoming Parade.
Public Works
LINESTRING(-86.5235295651801 39.17897812491182,-86.5235295651801 39.168498251876485)
House Move - 17th St, Monroe St, 11th St, Adams St, Fountain Dr, 8th St From 17th and Fee to 1670 W 8th via 17th St, Monroe St, 11th St, Adams St, Fountain Dr, and 8th St October 14, 2018 06:30 am to 14:00 pm
House Move for Habitat For Humanity. Streets along the route will be closed to through traffic while the house is in the area. Officers will assist with directing traffic.
Planning & Transportation
LINESTRING(-86.5188673861084 39.17877659334627,-86.54710568261719 39.178976195389026,-86.54710568261719 39.1731209666458,-86.54985226464844 39.17318750607495,-86.54961623025515 39.169660829564776,-86.5502385027466 39.169927,-86.55064619851684 39.16961092249605,-86.556074989563 39.16961092249605)
Windsor Private Subdivision Thames Drive, Wexford Court and Duxbury Drive October 15, 2018 to October 19, 2018
We will be paving the roads in this subdivision. Weather Permitting. Please use caution while in this area, the work will be performed under flagging operations.
Monroe County Highway Department
LINESTRING(-86.51783601350647 39.27650366712908,-86.5179862172113 39.27710163831327,-86.51828662462097 39.27755011335205,-86.51897327012878 39.27783248505173,-86.52002469606262 39.27773282458179,-86.52090446061949 39.27778265483448,-86.52148381776672 39.27769960439366,-86.52184859819275 39.27779926491084,-86.5221275479303 39.27793214537991,-86.52223483629089 39.27814807560458,-86.52197734422545 39.27897857026605,-86.52197734422545 39.279327375087945,-86.52219192094665 39.27960973962419,-86.52232066697935 39.27997515086389,-86.52208463258604 39.28025751278906)
South Walnut Street Stormwater Culvert Replacement Project South Walnut Street, between East 1st Street and East Dodds Street October 15, 2018 07:30 am to 15:30 pm October 19, 2018
The City of Bloomington Utilities has scheduled a stormwater culvert replacement project, weather permitting. The west lane of South Walnut Street, between East 1st Street and East Dodds Street, will be closed to all traffic for the duration of the project. Signage is in place.
Utilities
LINESTRING(-86.53365172219848 39.159390821875036,-86.53366245103453 39.157410858598666)
East Heather Drive Water Line Project East Heather Drive, between South Pepper Chase Court and South Grasstree Court October 15, 2018 07:30 am to 15:30 pm
The City of Bloomington Utilities has scheduled a water line project, weather permitting. Signage and traffic control personnel will be present.
Utilities
LINESTRING(-86.52243604611408 39.126292743138436,-86.5233050818349 39.125801686271956)
Cherry Lane Between Fairfax Road and Dutcherman October 15, 2018 to October 16, 2018
We will be performing ditching for drainage improvements along this segment of roadway. No lane closures, but the crews will be working along the roadway. Please use caution in this area.
Monroe County Highway Department
LINESTRING(-86.51704348397818 39.09720113706834,-86.51350296807853 39.09713452579527,-86.51289142442313 39.09660995982077)
Old SR 37 South Between Rogers Street and Fairfax Road October 15, 2018 to October 16, 2018
Traffic will be restricted to one lane during the hours of 8:00 am and 3:00 pm for bridge maintenance activities. Please use caution while traveling in this area. This is weather permitting.
Monroe County Highway Department
POINT(-86.53341313785148 39.10325135716727)
Dutcherman Drive Cherry Lane to the dead end October 17, 2018 to October 18, 2018
We will be performing ditching for drainage improvements along this segment of roadway. No lane closures, but the crews will be working along the roadway. Please use caution in this area.
Monroe County Highway Department
LINESTRING(-86.51294314206902 39.09669813532926,-86.5099283391363 39.096656502993994)
1200 Blk of East 1st Street East 1st Street closed between South Ballantine Rd and South Highland Avenue from 7:00 a.m. to 3:00 pm October 17, 2018 to October 19, 2018
For tree and stump removal
Street
LINESTRING(-86.51772268061345 39.15927309141816,-86.5191148811699 39.15928101532708)
South Fess Street South Fess Street closed between East 1st Street and East Maxwell Lane from 7:00 a.m. to 3:00 p.m. October 18, 2018 to October 19, 2018
Tree and stump removal
Street
LINESTRING(-86.52593169589824 39.159325310133596,-86.52596490165892 39.15784371089441)
Ketcham Road Between Cedar Bluff Road and Thrasher Road October 22, 2018 to November 20, 2018
This section of road will be closed for a bridge preservation project. Detour routes will be posted.
Monroe County Highway Department
POINT(-86.56687334941265 39.034052265843684)
Thomas Road Vernal Pike and Ratliff Road October 22, 2018 to October 24, 2018
The segment of roadway will be under flagging conditions for perform ditching activities. Please use caution when traveling in the area.
Monroe County Highway Department
LINESTRING(-86.63010395837424 39.18901091011185,-86.63061894250511 39.21667962069523)
Tanglewood Road Union Valley Road to the dead end October 22, 2018
This road segment will have lane restrictions for paving activities. Please use caution while traveling in this area.
Monroe County Highway Department
LINESTRING(-86.592710934634 39.231206252453546,-86.59205289935568 39.23147218980213,-86.59166666125753 39.23150543189985,-86.59070106601217 39.23150543189985,-86.58855529880026 39.23157191604801,-86.58716055011251 39.231688263155746,-86.58580871676901 39.231787989094556,-86.5855941400478 39.23202068240067,-86.58533664798237 39.232220133191674,-86.58535810565449 39.23245282506474,-86.58555122470356 39.23268551616616,-86.58619495486715 39.232984689305624,-86.58623787021138 39.233250619914315,-86.58591600512959 39.233483308370154,-86.58570142840841 39.23381571911139,-86.58570142840841 39.234414054477185,-86.58574434375265 39.23474646080908,-86.5856799707363 39.23516196650937,-86.58570142840841 39.235610709902005,-86.58608766650654 39.23595973055649)
Leonard Springs Road, west SR 45 to Fullerton Pike October 22, 2018 to October 23, 2018
This segment of road will be closed for paving operations, weather permitting. Detour routes will be posted.
Monroe County Highway Department
LINESTRING(-86.61417683773827 39.12234630174399,-86.61336144619776 39.12221312665764,-86.58452233486962 39.12221312665764,-86.58340653591942 39.122712531933246,-86.58276280575583 39.12294558651692,-86.58254822903466 39.123345106866594)
Westernmost lane of S. Walnut between First Street and Dodds closed to facilitate culvert repair. South Walnut Street October 22, 2018 to October 26, 2018
Lane of South Walnut closed to facilitate culvert repair.
Utilities
LINESTRING(-86.5337014655196 39.159338197475364,-86.53369171173463 39.15714495597135)
Spicer Lane Garrison Chapel Road to dead end October 23, 2018 to October 24, 2018
Spicer Lane will be under flagging operations for paving activities. Weather permitting. Please use caution while traveling in this area.
Monroe County Highway Department
LINESTRING(-86.64290919839536 39.14166884623609,-86.64732947885189 39.14171877312762,-86.64797320901545 39.14164388277703,-86.64903536378534 39.141152932950206,-86.64927139817866 39.141036435878505,-86.64995804368645 39.14086446365846,-86.65005460321099 39.14078957239903,-86.65062323152213 39.14073964484851,-86.65622368394523 39.140797893654025)
IU Street Sprints Kirkwood Ave. between Lincoln Street and Indiana Avenue October 27, 2018
IU Street Sprints bicycle race
Public Works
LINESTRING(-86.5310338862002 39.166564028970384,-86.53105534387225 39.166564028970384,-86.52696229291553 39.166547392552246)
Snoddy Road Robin Road and Blue Bird Lane October 29, 2018 to October 31, 2018
This segment of roadway will have ditching operations performed under flagging conditions. Please use caution while in the area. Weather permitting.
Monroe County Highway Department
LINESTRING(-86.48957766366574 39.131680672236484,-86.48962057900998 39.133994242537284)
Dillman Road Between SR 37 and Victor Pike, at the bridge October 29, 2018 to October 30, 2018
This segment of roadway will be closed to perform bridge maintenance. Weather permitting.
Monroe County Highway Department
LINESTRING(-86.55925072503662 39.09302812912287,-86.55478383374813 39.0930380553132,-86.55446196866635 39.09312132423196,-86.55416156125668 39.09308801667626,-86.55371095014216 39.09292147866171,-86.55343200040463 39.09298809391473,-86.546114934212 39.09293813248087)
Woodyard Road Between Walcott Lane and Hartstrait Road October 29, 2018 to November 2, 2018
This segment of roadway will be closed between 8:00 am and 5:00 pm each day for the Town of Ellettsville Utilities to work on a water main project.
Monroe County Highway Department
LINESTRING(-86.60173811162758 39.20117296255634,-86.60408271284895 39.20434406400406,-86.60539034457744 39.20713443444217,-86.60575512500348 39.207982396934256,-86.60624865146222 39.20824842227299,-86.60893086047712 39.2082317957188,-86.60981062503399 39.2082317957188,-86.61056164355816 39.20833155498468,-86.61124828906597 39.2085643260539)
Popcorn Road Between Bennett Lane and Harrodsburg Road November 1, 2018
This section of roadway will be performing ditching operations under flagging conditions. Please use caution while traveling in the area. Weather permitting.
Monroe County Highway Department
LINESTRING(-86.55398990102226 39.011778861242334,-86.55293847508841 39.01202895530179,-86.55190850682669 39.01214566556021,-86.54506350942069 39.01201228239199)
Strainridge Road Between Chestnut St and North St November 1, 2018 07:00 am to 12:00 pm
This segment of roadway will be under lane restrictions for a drainage repair. The work will be performed under flagging conditions. Pleas use caution while in this area. Weather permitting.
Monroe County Highway Department
LINESTRING(-86.50781880672012 39.069688342731524,-86.50778125579393 39.06983827632996,-86.5075076704744 39.070317228746575)
N. Maple Grove Road North of West Maple Grove Road November 2, 2018
This segment of roadway will be under flagging operations to perform ditching work. Please use caution in the area. Weather permitting.
Monroe County Highway Department
LINESTRING(-86.56627406551559 39.24453131905659,-86.56625396147476 39.251313215144364,-86.56668311491714 39.251944633688,-86.56646853819596 39.253805623689516)
CANOPY OF LIGHTS Kirkwood Avenue between College Avenue and Walnut Streets November 23, 2018 14:00 pm to 21:00 pm
Kirkwood Avenue between College Avenue and Walnut Streets be closed on Friday, November 23th, to vehicular traffic and parking between 2:00 p.m. and 9:00 p.m.
Public Works
LINESTRING(-86.53486289018103 39.16659208199039,-86.5336827182145 39.16658283951182)
Holiday Market Showers Common, Showers Plaza, North Morton between 7th and 8th streets. November 24, 2018 07:00 am to 18:00 pm
Annual Holiday Market hosted by the City of Bloomington Department of Parks & Recreation.
Public Works
LINESTRING(-86.53612641099943 39.16950545616501,-86.53610763553633 39.16858008812795)

Please enable Javascript

To enjoy the best experience, please make sure Javascript is enabled, or switch to a browser that supports Javascript.

This service uses Javascript to display an interactive map of scheduled road closures, which helps visualize where roads are scheduled to close.