HOW DO I KNOW IF MY PROJECT IS APPROVED?

Upon project design approval, the City of Bloomington Utilities will issue an official letter of "Acceptance & Approval of Plans".  Once you receive this notification, you are ready to proceed to the next step.  If you wish to check on the status of your project review, you may contact your Project Review Team, call our Engineering Utilities Technician at (812)349-3676, or send an email to: UtilitiesPlanReview@bloomington.in.gov.

 

MY PROJECT IS APPROVED; NOW WHAT?

CBU requires a Pre-Construction Meeting to be held PRIOR to the start of construction.  Contact the Utilities Technician at (812)349-3676 or by email to schedule a meeting for your project. 

 

Required Attendees:

General Contractor / Site Crew Leader

 

Recommended Attendees:

Developer

Project Manager

Sub-contractor(s) for Water/Sewer/Storm Infrastructure Installation

 

Bring along your copy of the Final Set of Certified Plans which was Approved by CBU.

For more detailed information about this meeting and permitting, click on the Pre-Construction Requirements box below.