What is a Neighborhood Greenway?
Neighborhood Greenways are low-speed, low-volume, shared-space streets that support high comfort walking and bicycling connections. Our 2019 Transportation Plan designates several City streets for the design and installation of Neighborhood Greenway facilities as part of the Priority Bicycle Facilities Network. To design and install Neighborhood Greenways, the City follows the Staff-led Traffic Calming and Neighborhood Greenways process.
What should I expect?
Neighborhood Greenways are an important component of the community’s plans to support an improved quality of life and connectivity. Past Neighborhood Greenway projects have shown an increase in the number of people walking, rolling, and bicycling in the area.
Residents may still park and drive on the Neighborhood Greenway. Traffic calming devices such as speed bumps and bump outs reduce the likelihood that drivers will speed on these streets.
More information on the Traffic Calming and Greenways process.
Project Timeline
1. Informational Neighborhood Letter
Note: Letters were mailed to residents within 300ft of the project
2. Neighborhood Greenway Survey Completed
3. First Public Meeting: Project Scope and Objectives - Wednesday, May 10 at 5:30pm at Park Ridge East Park shelter
4. Second Public Meeting: Design Review and Feedback - Wednesday, August 2 at 5:30pm at Park Ridge East Park shelter
Note: Rain Date is scheduled for Thursday, August 3 at 5:30pm
5. Open Comment Period
6. Bicycle and Pedestrian Safety Commission Review: Monday, September 11 at 5:30pm
7. Construction is expected to begin in mid-March
Project Documents
(Disclaimer; all documents are for reference only. Official documents are located on OpenGov.)
Bid and Award Information
- Invitation to Bidders
- Bidding Packet
- Letting Date: 3:00 pm EST Friday, December 15th, 2023 in the McCloskey Room of City Hall at the Showers Building, 401 N. Morton Street, Bloomington, Indiana, and via Zoom by using the following link: https://bloomington.zoom.us/j/82966780199?pwd=LgizbHaY5etiwuTnuHGNgUrnbKrB0g.1
- Award Date: December 19th, 2023, regular meeting of the Board of Public Works which will be held in the Council Chambers of City Hall at the Showers Building, 401 N. Morton Street, Bloomington, Indiana, and via Zoom using the following link: https://bloomington.in.gov/boards/public-works, or a subsequent meeting of the Board of Public Works.
Bid Results 12/15/2023
E&B Paving LLC $368,905.00 - Awarded
For More Information
Hank Duncan, Bicycle and Pedestrian Coordinator, at hank.duncan@bloomington.in.gov or (812) 349-3529
Zac Rogers, Project Manager, Engineering Dept., 812.349.3913 or zac.rogers@bloomington.in.gov