This project will reconstruct the crosswalks and repave East Kirkwood Avenue from Walnut Street to Indiana Avenue.

Project Timeline:

  • Design: April 2019
  • Construction: April 2020 through June 2020

Maintenance of Traffic:

  • Some sidewalks will have intermittent closures with pedestrian walk-arounds in place.
  • The intersection of Lincoln and Kirkwood will remain closed to traffic through June 10th.
  • East Kirkwood Avenue from Walnut Street to Indiana Avenue will be closed to traffic beginning June 1st, 2020 through June 10th, 2020.  No parking will be allowed on Kirkwood Avenue during this time as construction crews mill, pave, and install pavement markings.

Construction Progress

Bidding Documents

Letting Date: November 20th, 2:00 PM

Plans

Bid Packet

Addendum #1

Bollards

 

Bidding (Closed)

A pre-bid meeting is scheduled for Friday November 8th, 2019.

Bid opening - November 20th, 2019 by 2:00PM.

E&B Paving (apparent low bidder)

  • Base Bid $750,976.95
  • Alternate #1 $96,606.00
  • Alternate #2 $210,275.00

The Project has been awarded to E&B Paving, INC.

Project Contact:

Roy Aten